Wexford: homes with planning permission that nobody has started
Data updated 3 Oct 2026 · register lag up to 7 days · sources & freshness
5,409 homes in 132 sites of 10 or more have been granted permission in Wexford since 2017. A commencement notice was lodged for 76% of them. 1,164 still have a live permission and no start; 138 of those lapse within a year, and 136 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2017 | 8 | 356 | 100% | 0 | — |
| 2018 | 21 | 657 | 98% | 10 | — |
| 2019 | 11 | 457 | 95% | 0 | 21 |
| 2020 | 10 | 458 | 87% | 0 | 60 |
| 2021 | 14 | 698 | 92% | 0 | 55 |
| 2022 | 11 | 468 | 64% | 168 | — |
| 2023 | 20 | 720 | 84% | 118 | — |
| 2024 | 9 | 341 | 78% | 75 | — |
| 2025 | 12 | 484 | 81% | 94 | — |
| 2026 | 16 | 770 | 9% | 699 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Work started 91 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Clonard Little 20221652 | 167 | 20 Mar 2023 | Started notice 9 Jan 2024 | |
| BALLYTEGAN & CLONATIN LOWER 20161456 | 133 | 19 Jun 2017 | Started notice 29 Mar 2018 | |
| Ballyboggan 20241132 | 99 | 26 Jun 2025 | Started notice 21 Apr 2026 | |
| Mulgannon 20230488 | 99 | 17 Dec 2024 | Started notice 1 Nov 2025 | |
| BALLYNAGEE 20200243 | 99 | 7 Oct 2020 | Started notice 8 Jul 2022 | |
| WHITEROCK SOUTH 20181380 | 98 | 9 Jan 2019 | Started notice 18 Feb 2019 | |
| Knockmullen & Mill Lands 20201177 | 97 | 26 May 2021 | Started notice 12 Nov 2021 | |
| St. John's 20200440 | 97 | 15 Apr 2021 | Started notice 24 Apr 2024 | |
| Ballytegan 20201540 | 96 | 26 May 2021 | Started notice 21 Nov 2023 | |
| SHINGAUN 20191686 | 95 | 16 Jun 2020 | Started notice 8 Jul 2020 | |
| SHINGAUN 20181364 | 94 | 9 Jan 2019 | Started notice 23 May 2019 | |
| Ballyboggan 20230150 | 93 | 15 May 2023 | Started notice 15 Apr 2024 | |
| Goreybridge 20241284 | 91 | 16 Apr 2025 | Started notice 21 Nov 2025 | |
| Greenville 20230607 | 89 | 13 Nov 2023 | Started notice 1 Jul 2024 | |
| CREAGH DEMESNE 20171607 | 89 | 25 Jun 2018 | Started notice 3 Apr 2018 | |
| Ballytegan Park 20211321 | 86 | 6 Apr 2022 | Started notice 28 Feb 2024 | |
| Shingaun 20210307 | 86 | 7 Sept 2021 | Started notice 17 Nov 2022 | |
| Coolballow 20250909 | 85 | 15 Oct 2025 | Started notice 20 Mar 2026 | |
| Greenville 20210904 | 83 | 15 Nov 2021 | Started notice 17 Jan 2022 | |
| Enniscorthy 20231184 | 81 | 28 Feb 2024 | Started notice 1 Jul 2024 | |
| WHITEROCK SOUTH 20191031 | 73 | 25 Aug 2020 | Started notice 9 Aug 2021 | |
| COOLCOTS 20180666 | 71 | 1 Nov 2018 | Started notice 10 Nov 2022 | |
| Killagoley 20211935 | 69 | 14 Mar 2022 | Started notice 23 Apr 2024 | |
| COOLCOTS 20190734 | 67 | 19 Aug 2019 | Started notice 1 Sept 2020 | |
| Coolcots Townparks 20200338 | 65 | 21 Sept 2020 | Started notice 25 Apr 2022 | |
| Goreybridge 20211573 | 64 | 25 May 2022 | Started notice 11 Sept 2023 | |
| CLONARD LITTLE 20180014 | 59 | 3 Apr 2018 | Started notice 4 Oct 2018 | |
| GOREYHILL 20180080 | 58 | 7 Jun 2018 | Started notice 20 Aug 2018 | |
| Bridgetown South 20251437 | 56 | 13 Apr 2026 | Started notice 14 Sept 2026 | |
| Ballowen or Ramsfortpark 20230397 | 55 | 23 Nov 2023 | Started notice 24 Apr 2024 | |
| MULGANNON 20171297 | 54 | 7 Feb 2018 | Started notice 27 Sept 2018 | |
| Coolcotts 20221131 | 53 | 13 Jul 2023 | Started notice 26 Aug 2024 | |
| Knockmullen 20210927 | 53 | 8 Sept 2021 | Started notice 29 Mar 2022 | |
| ENNISCORTHY 20170425 | 52 | 17 Jul 2017 | Started notice 23 Aug 2019 | |
| KNOCKMULLEN 20190030 | 51 | 10 Apr 2019 | Started notice 2 Jul 2020 | |
| GREENVILLE 20170565 | 48 | 18 Sept 2017 | Started notice 25 Mar 2019 | |
| CLONARD GREAT AND KILLEENS 20180241 | 46 | 18 Jul 2018 | Started notice 30 Sept 2019 | |
| Bridgetown South 20240627 | 45 | 22 Jan 2025 | Started notice 31 Aug 2026 | |
| Gorey Bridge 20201176 | 43 | 12 Apr 2021 | Started notice 2 Jun 2021 | |
| Healysland 20230644 | 42 | 18 Dec 2023 | Started notice 19 Mar 2024 | |
| Coolcots 20211495 | 40 | 11 Apr 2022 | Started notice 20 Mar 2024 | |
| RAMSTOWN LOWER 20161345 | 40 | 12 Apr 2017 | Started notice 17 May 2017 | |
| Ballygillane Little 20250516 | 39 | 4 Nov 2025 | Started notice 2 Apr 2026 | |
| CREAGH DEMESNE 20170652 | 36 | 18 Oct 2017 | Started notice 21 Nov 2017 | |
| Whiterock South 20210664 | 34 | 30 Aug 2021 | Started notice 30 Mar 2026 | |
| COOLCOTS 20190485 | 34 | 1 Jul 2019 | Started notice 6 Jan 2020 | |
| CASTLELAND 20180732 | 34 | 3 Dec 2018 | Started notice 26 Aug 2019 | |
| Enniscorthy 20240261 | 33 | 12 Aug 2024 | Started notice 28 Aug 2024 | |
| Townparks 20210576 | 32 | 4 Oct 2021 | Started notice 22 Apr 2022 | |
| BALLYTRAMON 20190312 | 32 | 15 Jul 2019 | Started notice 25 Nov 2022 | |
| GOREYBRIDGE 20180811 | 32 | 4 Sept 2018 | Started notice 12 Aug 2022 | |
| CREAGH DESMESNE 20181238 | 31 | 3 Dec 2018 | Started notice 15 Jun 2019 | |
| Maudlintown 20221053 | 28 | 3 Jul 2023 | Started notice 1 Aug 2023 | |
| ENNISCORTHY 20171337 | 28 | 26 Feb 2018 | Started notice 28 Mar 2018 | |
| Ballygillane Big 20220866 | 27 | 28 Nov 2022 | Started notice 19 Mar 2024 | |
| CASTLEBRIDGE 20200166 | 25 | 25 Jun 2020 | Started notice 5 Apr 2021 | |
| WHITEROCK SOUTH 20171679 | 25 | 20 Mar 2018 | Started notice 25 Jun 2018 | |
| Ballygillane Big 20220305 | 24 | 11 Apr 2024 | Started notice 21 Sept 2026 | |
| CROSSTOWN 20160970 | 24 | 5 Sept 2017 | Started notice 13 Aug 2018 | |
| GOREY HILL 20181088 | 20 | 1 Nov 2018 | Started notice 2 Nov 2018 |
1–60 of 91Next 60 →
How it is counted
- A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'WEXFORD' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 3 Oct 2026, 23:01
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC-BY-4.0 | 3 Oct 2026, 23:01 | open |
| An Coimisiún Pleanála case list | CC-BY-4.0 | 3 Oct 2026, 23:01 | open |
| Building Control Management System commencement notices | CC-BY-4.0 | 3 Oct 2026, 23:01 | open |
Recomputed weekly from the store; last built 3 Oct 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.
Big developments by name · Where Dublin is building · Sources & freshness