Brinny Innishannon Co. Cork
Approved, built and signed off.
- 15 Mar 2018Received
- 9 May 2018Conditional
- 20 Jun 2018Final approval
- 6 Jul 2018Building started
- 11 Jun 2020Signed off
- Status
- Building started
- Decision
- Conditional · 9 May 2018
- Council
- Cork County Council
- Type
- PERMISSION
- Site
- 7,534 m²
Live near Brinny Innishannon Co. Cork?
Everything else planned on your street, in one report.
Check my streetWhat’s proposed
An extension to the existing Building 21 (Planning Ref. 17/4830) and associated works as follows: The works include the construction of a new 2 storey extension with ground floor mezzanine to the East elevation. The extension will comprise a freezer room, staging areas and the provision of roof mounted plant within the curtilage of a new parapet. The extension has a total floor area of 592 square metres and is 15.7 metres high. The works also include landscaping, underground and overground utilities, yards and associated siteworks. The works also include new external items of plant and equipment. The application consists of an activity for which an Industrial Emissions license under Part IV of the Environmental Protection Agency Act 1992 (as amended) is required
Planning details
- Reference
- 18/4642
- Local authority
- Cork County Council
- Status
- Commenced · register status “APPLICATION FINALISED”
- Received
- 15 Mar 2018
- Observations close
- 19 Apr 2018 (closed 3091 days ago)
- Decision due
- 9 May 2018 · decided 9 May 2018
- Decision
- Conditional on 9 May 2018
- Proposed development
- An extension to the existing Building 21 (Planning Ref. 17/4830) and associated works as follows: The works include the construction of a new 2 storey extension with ground floor mezzanine to the East elevation. The extension will comprise a freezer room, staging areas and the provision of roof mounted plant within the curtilage of a new parapet. The extension has a total floor area of 592 square metres and is 15.7 metres high. The works also include landscaping, underground and overground utilities, yards and associated siteworks. The works also include new external items of plant and equipment. The application consists of an activity for which an Industrial Emissions license under Part IV of the Environmental Protection Agency Act 1992 (as amended) is requiredAs published by the register.
- Site area
- 7,534 m² from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Nearby 18 · 500 m · 5 years
- WithdrawnKilmore, Brinny, Innishannon, Co. Cork.
- WithdrawnBrinny, Innishannon, Co.Cork
- CommencedBrinny, Innishannon, Co. Cork
- GrantedBrinny, Innishannon, Co. Cork.
- GrantedBrinny, Innishannon, Co. Cork, T12 RD82
- WithdrawnMSD Brinny Innishannon Co. Cork
- GrantedKilmore Brinny Co Cork
- WithdrawnKilmore Brinny Co Cork
Show all 18
- WithdrawnKilmore Brinny Co Cork
- GrantedA site of c. 8.75 ha located at lands Brinny Innishannon Co.Cork
- GrantedBrinny Innishannon Co. Cork
- WithdrawnKilmore Brinny Co. Cork
- WithdrawnKilmore Brinny Co. Cork
- GrantedBrinny Innishannon Co.Cork
- WithdrawnKilmore Brinny Co.Cork
- GrantedBrinny Innishannon Co.Cork
- GrantedBrinny Innishannon Co. Cork
- WithdrawnBrinny Innishannon Co. Cork
Homes nearby
Building started
- 6 Jul 2018 · Builder told the council work was starting CN0041126CC
Zoning
Not zoned in the current plan.
Protections nearby 250 m
No mapped flood area nearby.
- NIAH-recorded building · 1
Where this comes from
National planning feed (NPAD), fetched 18 Sept 2026, 15:44.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |
Summary
18/4642 is a planning application to Cork County Council for an extension to the existing Building 21 (Planning Ref. 17/4830) and associated works as, received on 15 Mar 2018; permission was granted with conditions on 9 May 2018.