Withdrawn or invalid.

  1. 11 Sept 2020Received
  2. 21 Sept 2020Application declared inva
Status
Withdrawn or invalid
Decision
Application declared inva · 21 Sept 2020
Council
Dublin City Council
Type
Permission
Site
2,034 m²

Live near 180 182?

Everything else planned on your street, in one report.

Check my street

What’s proposed

The proposed development involves site clearance and levelling works, including the demolition of all existing buildings on site and the construction of a 148 bed hotel that ranges in height between 1 and 7 storeys above three lower ground levels (along the southern part of site) including ancillary staff and guest facilities, plant, storage and waste/refuse storage areas. An ESB substation is proposed at ground floor level at the south-eastern corner of the proposed building. Guest / pedestrian access is provided along the southern frontage onto James Street with Guest Lobby at ground floor. A combination of hard and soft landscaping measures are proposed along all elevations to enhance areas of public realm and ancillary amenity spaces. The proposed building includes for the provision of sustainable drainage measures together with the provision of green roofs. Permission is also sought for associated signage. Development of an aparthotel was previously permitted at this site, under Planning Register 2950/17 & ABP300057-17

Planning details

Reference
3372/20
Local authority
Dublin City Council
Status
Withdrawn or invalid · register status “Decision Notice Issued”
Received
11 Sept 2020
Observations close
16 Oct 2020 (closed 2179 days ago)
Decision due
5 Nov 2020 · decided 21 Sept 2020
Decision
Application declared inva on 21 Sept 2020
Proposed development
The proposed development involves site clearance and levelling works, including the demolition of all existing buildings on site and the construction of a 148 bed hotel that ranges in height between 1 and 7 storeys above three lower ground levels (along the southern part of site) including ancillary staff and guest facilities, plant, storage and waste/refuse storage areas. An ESB substation is proposed at ground floor level at the south-eastern corner of the proposed building. Guest / pedestrian access is provided along the southern frontage onto James Street with Guest Lobby at ground floor. A combination of hard and soft landscaping measures are proposed along all elevations to enhance areas of public realm and ancillary amenity spaces. The proposed building includes for the provision of sustainable drainage measures together with the provision of green roofs. Permission is also sought for associated signage. Development of an aparthotel was previously permitted at this site, under Planning Register 2950/17 & ABP300057-17
As published by the register.
Site area
2,034 m² from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name

Nearby 100 · 500 m · 5 years

Show all 100

Explore this area on the map →

Homes nearby

Development land nearby

From Buildable, our sister site for development land in Dublin.

See all development land near here →

Zoning

Zone Z1 - DEV PLAN 2022-2028

R2 — Existing residential

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

Protections nearby 250 m

Flood area nearby (OPW maps). floodinfo.ie ↗

  • NIAH-recorded building · 17
    Irish Museum of Modern Art; gate lodge
  • Radon risk area · 1
    About 1 in 20 homes in this area is likely to have high radon levels
  • Recorded monument · 11
    House - 18th/19th century; Bridge

Where this comes from

National planning feed (NPAD), fetched 11 Sept 2026, 18:51.

Source: npad · fetched 11 Sept 2026, 18:51
SourceLicenceFetchedLink
npadCC-BY-4.011 Sept 2026, 18:51open
Summary

3372/20 is a planning application to Dublin City Council for the proposed development involves site clearance and levelling works, including the, received on 11 Sept 2020; it was withdrawn on 21 Sept 2020.