PlanningRegister.ie
Dublin City Council · 3507/20

45-47, Cuffe Street (Greenside House), Dublin 2

Approved. Building started.

  1. 6 Oct 2020Received
  2. 30 Nov 2020Split decision(permission
  3. 18 Dec 2020Appealed
  4. 30 Apr 2021Appeal: Approved with conditions
  5. 30 Apr 2021Final approval
  6. 29 May 2024Building started
Status
Building started
Decision
Split decision(permission · 30 Nov 2020
Council
Dublin City Council
Type
Permission
Site
796 m²
Appeal
ACP 308961 · Approved with conditions

Live near 45-47?

Everything else planned on your street, in one report.

Check my street

What’s proposed

The application site also fronts Montague Court and Protestant Row. The application seeks amendments to the development permitted under Reg.Ref. 2142/20. The amendments consist of the following: i) Provision of additional floor to permitted development (providing for nine storey over lower ground floor/ basement with mezzanine between upper ground floor and first floor) ii) Minor extensions of floor plate at various levels iii) Revisions to elevations and entrances iv) All associated site development works and consequential amendments (including bicycle parking provision) to permitted scheme. v) The amendments provide for an increase in Gross Floor Area to the permitted scheme of 504 sq.m with an overall proposed GFA of 5221.40 sq.m

Planning details

Reference
3507/20
Local authority
Dublin City Council
Status
Commenced · register status “Appeal Decided”
Received
6 Oct 2020
Observations close
10 Nov 2020 (closed 2156 days ago)
Decision due
30 Nov 2020 · decided 30 Nov 2020
Decision
Split decision(permission on 30 Nov 2020
Proposed development
The application site also fronts Montague Court and Protestant Row. The application seeks amendments to the development permitted under Reg.Ref. 2142/20. The amendments consist of the following: i) Provision of additional floor to permitted development (providing for nine storey over lower ground floor/ basement with mezzanine between upper ground floor and first floor) ii) Minor extensions of floor plate at various levels iii) Revisions to elevations and entrances iv) All associated site development works and consequential amendments (including bicycle parking provision) to permitted scheme. v) The amendments provide for an increase in Gross Floor Area to the permitted scheme of 504 sq.m with an overall proposed GFA of 5221.40 sq.m
As published by the register.
Site area
796 m² from the mapped boundary, not the council's figure
Applicant
Not published — the national feed carries no applicant name

Nearby 297 · 500 m · 5 years

Show all 297

Explore this area on the map →

Homes nearby

Development land nearby

From Buildable, our sister site for development land in Dublin.

See all development land near here →

Appeal

ACP 308961 · Planning Appeal · decided · Approved with conditions 30 Apr 2021
received by the Commission 18 Dec 2020 · inspector's report · board order

Building started

  • 29 May 2024 · Builder told the council work was starting CN0115363DC

Zoning

Zone Z5 - DEV PLAN 2022-2028

M2 — Major town centre

The main town centre — retail, offices, civic uses, apartments.

Protections nearby 250 m

No mapped flood area nearby.

  • NIAH-recorded building · 94
    Superintendent's Lodge; college
  • Radon risk area · 1
    About 1 in 20 homes in this area is likely to have high radon levels
  • Recorded monument · 25
    Gateway; Church

Where this comes from

National planning feed (NPAD), fetched 11 Sept 2026, 18:51.

Source: npad · fetched 11 Sept 2026, 18:51
SourceLicenceFetchedLink
npadCC-BY-4.011 Sept 2026, 18:51open
Summary

3507/20 is a planning application to Dublin City Council for the application site also fronts Montague Court and Protestant Row. The application, received on 6 Oct 2020; the council recorded "SPLIT DECISION(PERMISSION" on 30 Nov 2020.