Approved in Jan 2024. Building started in 2024.

  1. 24 Oct 2023Received
  2. 14 Dec 2023Approved
  3. 24 Jan 2024Final approval
  4. 7 Nov 2024Building started
Status
Building startedi
Decision
Approved · 14 Dec 2023
Council
Dublin City Council
Type
Permission
Site
135 m²

What’s proposed

PERMISSION:The development will consist of extending the existing ground floor level extension and constructing a new first floor level extension all to the rear, and upgrading the main house internally, all to an existing two-storey mid-terrace dwelling

Planning details

Reference
4681/23
Local authority
Dublin City Council
Status
Commenced · register status “Decision Notice Issued”
Received
24 Oct 2023
Decision due
18 Dec 2023 · decided 14 Dec 2023
Decision
Grant permission on 14 Dec 2023
Site area
135 m² from the mapped boundary, not the council's figure

Live near 21 The Square?

Everything else planned on your street, in one report.

Check my street
Council register ↗

Nearby 18 · 500 m · 12 months

Distance
Time
Show all 18

Explore this area on the map →

Homes nearby

Development land nearby

See all development land near here →

Building started

  • 7 Nov 2024 · Builder told the council work was starting (opted out of the finish sign-off) CN0121703DC

Zoning

Zone Z1 - DEV PLAN 2022-2028

R2 — Existing residential

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

Protections nearby 250 m

Flood area nearby (OPW maps). floodinfo.ie ↗

Where this comes from

National planning feed (NPAD), fetched 11 Sept 2026, 18:51.

Source: National Planning Application Database · fetched 11 Sept 2026, 18:51
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.011 Sept 2026, 18:51open
Summary

4681/23 is a planning application to Dublin City Council for PERMISSION:The development will consist of extending the existing ground floor level, received on 24 Oct 2023; permission was granted on 14 Dec 2023.