Approved in Apr 2023. Building started in 2024.

  1. 6 Sept 2022Received
  2. 1 Feb 2023Conditional
  3. 13 Apr 2023Final approval
  4. 4 Apr 2024Building started
Status
Building startedi
Decision
Conditional · 1 Feb 2023
Council
Kildare County Council
Type
PERMISSION
Site
856 m²

What’s proposed

development of 4 No. 20 kV ESB double substations at four sites of c. 591 sqm in total (Site 1, c. 138 sqm adjacent to Building 4; Site 2, c. 138 sqm adjacent to Building 2 and Building 5; Site 3, c. 138 sqm adjacent to Building 5; and Site 4, c. 177 sqm partially within Building 9, at the Kildare Innovation Campus (formerly known as the Hewlett Packard Campus) Barnhall Road, Leixlip, Co. Kildare. The wider Kildare Innovation Campus is c. 80 hectares. The wider Campus is principally bounded by: Barnhall Road to the north; Celbridge Road to the east; Barnhall Rugby Football Club to the south; and grounds associated with Castletown House to the west. The proposed development will consist of: the construction of 3 No. standalone ESB double substations and associated LV switch rooms (Substations No. 1-3) of c. 3m in height, c. 4.8m in depth, and c. 17.8m in width, with an individual gross floor area of 57.5 sqm; and all associated works above and below ground. Substation No. 4 (gross floor area of 57.5 sqm) will include: internal alterations to the existing Campus Building No. 9; associated LV switch rooms; the removal of existing louvre and replacement with substation access doors on the southeast elevation; access path; and all associated works above and below ground. The cumulative gross floor area of the development will be 230 sqm

Planning details

Reference
221096
Local authority
Kildare County Council
Status
Commenced · register status “APPLICATION FINALISED”
Received
6 Sept 2022
Decision due
15 Feb 2023 · decided 1 Feb 2023
Decision
Conditional on 1 Feb 2023
Site area
856 m² from the mapped boundary, not the council's figure

Live near Kildare Innovation Campus?

Everything else planned on your street, in one report.

Check my street
Council register ↗

Nearby 3 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Building started

  • 4 Apr 2024 · Builder told the council work was starting (seven-day notice) SN0009936KE
  • 4 Apr 2024 · Builder told the council work was starting (seven-day notice) SN0009937KE
  • 4 Apr 2024 · Builder told the council work was starting (seven-day notice) SN0009938KE

Protections nearby 250 m

  • EPA-licensed facility · 3
    Hewlett Packard (Manufacturing) Limited; P1222
  • Recorded monument · 1
    Fulacht fia

Where this comes from

National planning feed (NPAD), fetched 28 Oct 2026, 01:34.

Source: National Planning Application Database · fetched 28 Oct 2026, 01:34
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.028 Oct 2026, 01:34open
Summary

221096 is a planning application to Kildare County Council for development of 4 No. 20 kV ESB double substations at four sites of c. 591 sqm in total, received on 6 Sept 2022; permission was granted with conditions on 1 Feb 2023.