Ballydine , Kilsheelan , Clonmel
- 14 Sept 2021Received
- 2 Feb 2022Conditional
- 8 Mar 2022Final grant
- 7 Mar 2032Permission expires
- Status
- Granted with conditions
- Decision
- Conditional · 2 Feb 2022
- Council
- Tipperary County Council
- Type
- PERMISSION
- Site
- 7.49 ha
What’s proposed
development on this site of circa c.7.48 hectares. The development will consist of a 10-year permission for the construction of a Solar PV Energy Development comprising installation of Solar Photovoltaic (PV) panels on ground mounted frames/support structures within existing field boundaries, underground cabling and ducting, 1 no. customer control building, 1 no. switchgear and transformer building, site perimeter (stock proof) security fence and associated access gates, maintenance track, landscaping and all associated site development works. A temporary construction compound will be provided and vehicular access is via the existing access route from N24 serving the Ballydine 110kv substation to south-west of the site. This application relates to development for the purposes of an acitivity requiring a licence under the Industrial Emissions Directive. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with the application
211365 is a planning application to Tipperary County Council for development on this site of circa c.7.48 hectares. The development will consist of a, received on 14 Sept 2021; permission was granted with conditions on 2 Feb 2022.
Planning details
- Reference
- 211365
- Local authority
- Tipperary County Council
- Status
- Granted with conditions · register status “APPLICATION FINALISED”
- Received
- 14 Sept 2021
- Observations close
- 19 Oct 2021 (closed 1795 days ago)
- Decision due
- 8 Feb 2022 · decided 2 Feb 2022
- Decision
- Conditional on 2 Feb 2022
- Proposed development
- development on this site of circa c.7.48 hectares. The development will consist of a 10-year permission for the construction of a Solar PV Energy Development comprising installation of Solar Photovoltaic (PV) panels on ground mounted frames/support structures within existing field boundaries, underground cabling and ducting, 1 no. customer control building, 1 no. switchgear and transformer building, site perimeter (stock proof) security fence and associated access gates, maintenance track, landscaping and all associated site development works. A temporary construction compound will be provided and vehicular access is via the existing access route from N24 serving the Ballydine 110kv substation to south-west of the site. This application relates to development for the purposes of an acitivity requiring a licence under the Industrial Emissions Directive. A Natura Impact Statement (NIS) will be submitted to the Planning Authority with the applicationAs published by the register.
- Site area
- 7.49 ha from the mapped boundary, not the council's figure
- Applicant
- Not published — the national feed carries no applicant name council register
Full planning report for 52.36273, -7.51930
Zoning, appeals, sold prices, flood and heritage — the whole area in one PDF.
No account, no payment. Not a statutory planning search.
Appeal
Not appealed.
Commencement
No commencement notice matched to this reference.
Zoning at the site
No zoning objective covers this site in the current plan.
Designations within 250 m
No OPW flood extent nearby.
No other designation nearby.
Provenance
Register row from the national planning applications feed (NPAD), fetched 18 Sept 2026, 15:44 (store id 470728). Deadlines were computed by the store from the received / decided dates under the Planning and Development Act 2000 and are recorded as events, not recomputed here. Council register: http://www.eplanning.ie/TipperaryCC/AppFileRefDetails/211365/0.
Source: npad · fetched 18 Sept 2026, 15:44
| Source | Licence | Fetched | Link |
|---|---|---|---|
| npad | CC-BY-4.0 | 18 Sept 2026, 15:44 | open |