Glasnevin Autos
101 apartmentsGlasnevin, Dublin City Council
Also known as 54 Glasnevin Hill.
Building progress as the Dublin councils report it, Q1 2026
All 101 permitted homes are built (Q1 2026).
completed · under construction · not started · 0 houses and 101 apartments permitted
Quarter by quarter
| Quarter | Permitted | Under construction | Completed | Completed share |
|---|---|---|---|---|
| Q2 2025 | 101 | 101 | 0 | |
| Q3 2025 | 101 | 101 | 0 | |
| Q4 2025 | 101 | 101 | 0 | |
| Q1 2026 | 101 | 0 | 101 |
- Status
- Completed · activity on site: completed
- Decision
- Grant · 13 Apr 2021
- Size
- 101 apartments
- Site
- 4,577 m²
The scheme
This application proposes the development of 101 residential units at the site of Glasnevin Autos on Glasnevin Hill in Dublin 9. The project involves the construction of apartments on a 0.46 hectare site.
it proposes 101 residential units
On this list because it is 20 homes or more on the Dublin councils' housing pipeline. Name and summary derived from the councils' pipeline record on 27 Sept 2026; the facts are the councils'.
The site 4,577 m²
Boundary of Glasnevin Autos as the Dublin councils map it in the housing pipeline.
Planning applications inside the site 5 applications in the last 10 years
- WithdrawnUnit 3 & 4, Block 2, Millfield View, Glasnevin Hill, Dublin 9
- CommencedMarian Nursing Home, Old Finglas Rd. Glasnevin, Dublin 11
- WithdrawnMarian Nursing Home, Old Finglas Road, Glasnevin, Dublin 11
- Granted52, Glasnevin Hill, Glasnevin, Dublin 9, D09 Y2W7
- WithdrawnSite of c. 0.4496 hectares, Glasnevin Hill, Glasnevin, Dublin 9
Appeals inside the site 3 with An Coimisiún Pleanála
- Granted with conditionsBallymun/Finglas to Dublin City Centre
- Granted with conditionsNo. 54 Glasnevin Hill and "Ardmore" with lands adjacent thereto, No. 38 Glasnevin Hill, No. 52 Glasnevin Hill, lands to the rear of Nos. 48, 50 and 52 Glasnevin Hill, and Nos. 40 and 42 Glasnevin Village, Dublin 9. (www.BeechviewSHD.com)
- Granted with conditionsGlasnevin Autos, 54, Glasnevin Hill, Glasnevin, Dublin 9
Building work started inside the site 3 commencement notices
- CommencedMillfield View, Glasnevin Hill, Glasnevin, Dublin 9
- CommencedMillfield View, Glasnevin Hill, Dublin 9, D09 K7Y2
- CommencedGlasnevin Hill, Dublin 9, D09 K7Y2
Planning timeline 6 steps
- 15 Dec 2020Application lodged — SHD
- 13 Apr 2021Council decision — Grant
- 13 Apr 2021Final grant of permission
- Q1 2023Building started — Activity on site
- Q1 2026Site completed — Site completed
- 26 May 2026Permission expires (estimate) — Estimated permission expiry
Other big developments nearby within 2 km
- Balnagowan House · 78 homes · 5 storeys · 265 m away
- Glenavon House · 52 homes · 6 storeys · 368 m away
- Rivermount Cottages · 99 homes · 5 storeys · 1.2 km away
- 116-120 Drumcondra Road Upper · 122 homes · 5 storeys · 1.2 km away
- Clonliffe Family Hub · 50 homes · 3 storeys · 1.5 km away
- Collins Avenue Extension Development · 67 homes · 6 storeys · 1.5 km away
- Former Carmelite Convent of the Incarnation · 99 homes · 6 storeys · 1.6 km away
- Former Des Kelly Site · 96 homes · 12 storeys · 1.6 km away
Planning report for Glasnevin Autos
Every application, appeal and deadline within 500 m, with zoning and heritage, in one report.
No account, no payment. Not a statutory planning search.
Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.