Building: first homes signed off Nov 2026, of 47 homes; approved Feb 2026.

A start notice was filed, but the councils' Q2 2026 return counts none of the 47 homes started yet.

Castlethorn Developments Luttrellstown LimitedDublin 15, Fingal County Council

Email me when the next phase is lodged

Status
Start notice filed
Council decision
Approved · 20 Nov 2025
Approved
3 Feb 2026 · final grant
Uses
residential
Applicant
Castlethorn Developments Luttrellstown Limited · 7 planning applications, 80% granted
Site
2.09 ha
Appeal
ACP 500486 · Other · 12 Jun 2026

Building progress councils’ figures, Q2 2026

  1. 2026Approved
  2. 2026Start notice filed
  3. 2026First homes signed off1 sign-off
Quarter by quarter
QuarterPermittedUnder constructionCompletedCompleted share
Q4 2025000
Q1 2026000
Q2 20264700
Source and licence

The scheme

Castlethorn Developments Luttrellstown Limited proposes a residential development on a site in the townlands of Kellystown and Porterstown, Dublin 15. The project involves the construction of 47 units on a site area of approximately 2.17 hectares.

What the register says

Permission at site (c. 2.17 ha) in the townlands of Porterstown and Kellystown, Dublin 15. The site (Luttrellstown Gate Phase 2 - Site B) is located within the Kellystown Local Area Plan development boundary. The site is generally bounded to the north by the Dublin-Maynooth rail line, to the south and east by permitted Strategic Housing Development (ABP-312318-21 as amended by LRD0034/S3) known as Luttrellstown Gate (Phase 1), with the shared boundary defined by hedgerow, and to the west by concurrent planning application known as Luttrellstown Gate (Phase 2 - Site A). The site boundary extends to the southwest to accommodate foul drainage to a permitted foul pumping station and surface water drainage to a permitted attenuation pond (both on Phase 1 lands permitted under ABP-312318-21 as amended by LRD0034/S3). The proposed development comprises 47 no. dwellings, in a mix of houses and duplex units/own-door apartments, ranging from 2-3 storeys in height, including 35 no. houses (31 no. 3-bed and 4 no. 4-bed), and 12 no. duplex/apartment units with balconies (8 no. 1-bed and 4 no. 2-bed); and all associated and ancillary site development, landscaping and boundary treatment works, including: 54 no. surface car parking spaces; 152 no. bicycle parking spaces for mid-terrace and duplex units; Bin stores; Private, communal and public open space; Public lighting; Minor amendments to the permitted surface water attenuation pond. Vehicular access is provided off the existing Kellystown Link Road via the internal roads of Luttrellstown Gate (Phase 1)…

Cut short by the council feed. Full text ↗

Summary from the register record.

Planning timeline 7 steps
  • 26 Sept 2025
    Application lodged — Standard
  • 17 Dec 2025
    Appealed to An Coimisiún Pleanála — PL-500486-DF-25
  • 3 Feb 2026
    Council decision — Grant
  • 3 Feb 2026
    Commission decision — Granted
  • 3 Feb 2026
    Final approval
  • 22 Jul 2026
    Building started
  • 15 Mar 2031
    Approval runs out (estimate)

The site 2.09 ha

Boundary of Kellystown and Porterstown Lands as the Dublin councils map it in the housing pipeline.

Planning applications inside the site 6 applications in the last 10 years

Appeals inside the site 8 with An Coimisiún Pleanála
Commencement notices inside the site 2

Other big developments nearby within 2 km

Start notices are matched from the national building control register; a start on site can be missed.

Everything within 1 km on the map →

Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.