Mabestown Wood, Malahide
Approved May 2025: 48 homes; building not started (Q3 2025).
Start notices are matched from the national building control register; a start on site can be missed.
Beakonshaw Mabes LimitedMalahide, Fingal County Council
How the homes are counted
- 48 homes permitted (the Dublin councils' housing pipeline, Q3 2025).
- On the planning register as Mabestown (F24A/0675E).
Also known as Lands at Mabestown.
- Status
- Approved · no start notice yet
- Decision
- Approved · 27 Mar 2025
- Uses
- residential
- Applicant
- Beakonshaw Mabes Limited
- Site
- 1.82 ha
Building progress councils’ figures, Q3 2025
completed · under construction · not started · 32 houses and 16 apartments permitted
Quarter by quarter
| Quarter | Permitted | Under construction | Completed | Completed share |
|---|---|---|---|---|
| Q2 2025 | 48 | 0 | 0 | |
| Q3 2025 | 48 | 0 | 0 |
Source and licence
The scheme
Beakonshaw Mabes Limited proposes a residential development on lands at Mabestown, Malahide Road, Malahide. The project involves the construction of 48 units on a 1.82 hectare site.
What the register says
Beakonshaw Mabes Limited intend to apply for PERMISSION for developmen…
Cut short by the council feed. Full text ↗
Summary from the register record.
Planning timeline 4 steps
- 29 Nov 2024Application lodged — Standard
- 27 Mar 2025Council decision — Grant
- 9 May 2025Final approval
- 23 Jun 2030Approval runs out (estimate)
The site 1.82 ha
Boundary of Mabestown Wood, Malahide as the Dublin councils map it in the housing pipeline.
Planning applications inside the site 2 applications in the last 10 years
Appeals inside the site 6 with An Coimisiún Pleanála
- Under appealLocated off the coast of Counties Dublin, Meath and Louth
- Granted with conditionsLands at Mabestown, Malahide Road (R107), Malahide, Co. Dublin
- OtherBack Road, Malahide, Co. Dublin
- OtherAuburn, Streamstown, Malahide, Co. Dublin
- OtherAuburn, Streamstown, Malahide, Co. Dublin
- OtherAuburn, Streamstown, Malahide, Co. Dublin
Other big developments nearby within 2 km
- Including part of the grounds of Lamorlaye · 147 m away
- Auburn House · withdrawn or invalid · 216 m away
- Back Road · approved 2025, no start notice · 745 m away
- Back Road and Kinsealy Lane · 745 m away
- Kinsealy Lane · building started 2026 · 851 m away
- Teagasc Research Centre · building started 2026 · 1.5 km away
- Seamount Road and Seamount Abbey · approved 2023, no start notice · 1.9 km away
Start notices are matched from the national building control register; a start on site can be missed.
Something wrong on this scheme page, or a record you want corrected or removed? Contact us and we will check it against the source.