Cork County: homes with planning permission that nobody has started
Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness
15,104 homes in 301 sites of 10 or more have been granted permission in Cork County since 2017. A commencement notice was lodged for 55% of them. 5,638 still have a live permission and no start; 496 of those lapse within a year, and 1,103 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2017 | 15 | 641 | 74% | 0 | 165 |
| 2018 | 23 | 1,112 | 71% | 0 | 317 |
| 2019 | 37 | 1,169 | 78% | 0 | 263 |
| 2020 | 20 | 642 | 85% | 0 | 99 |
| 2021 | 40 | 1,554 | 67% | 261 | 259 |
| 2022 | 45 | 1,931 | 65% | 675 | — |
| 2023 | 39 | 1,936 | 73% | 528 | — |
| 2024 | 24 | 1,607 | 62% | 611 | — |
| 2025 | 30 | 1,948 | 13% | 1,696 | — |
| 2026 | 28 | 2,564 | 27% | 1,867 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Work started 180 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Knockgriffin 21/7265 | 434 | 16 Jun 2023 | Started notice 2 Oct 2024 | |
| Knockgriffin Midleton Co.Cork 22/6627 | 330 | 25 Apr 2024 | Started notice 19 Feb 2026 | |
| Broomfield West Midleton Co.Cork 23/6277 | 272 | 11 Apr 2024 | Started notice 16 Dec 2024 | |
| Cloheen Clonakilty Co. Cork 25/324 | 246 | 7 May 2026 | Started notice 13 Jul 2026 | |
| 'Castle Heights' Kilmoney Carrigaline Co.Cork 17/4176 | 224 | 3 May 2018 | Started notice 10 Jun 2019 | |
| Knockbrogan 25/6376 | 212 | 14 May 2026 | Started notice 22 Jul 2026 | |
| Maple Woods 23/4450 | 125 | 8 May 2023 | Started notice 28 Feb 2024 | |
| "Clonmore" Ballyviniter Lower Mallow Co. Cork 16/6949 | 108 | 5 Mar 2018 | Started notice 8 Mar 2019 | |
| Broomfield Village Broomfield East and Broomfield West Midle 16/6818 | 100 | 11 Jul 2017 | Started notice 21 Apr 2026 | |
| Carrightohill Carrigtwohill Co. Cork 23/4514 | 99 | 26 Jan 2024 | Started notice 16 Apr 2024 | |
| Lakeview Castleredmond Midleton Co.Cork 22/4753 | 99 | 22 Aug 2022 | Started notice 27 Mar 2024 | |
| Church Bay Road Crosshaven Co. Cork 21/5852 | 99 | 28 Feb 2022 | Started notice 1 Nov 2022 | |
| Janeville Shannonpark Carrigaline Co. Cork 21/5556 | 98 | 16 Dec 2021 | Started notice 1 Aug 2023 | |
| Lakeview Castleredmond Midleton Co.Cork 21/7428 | 97 | 29 Jul 2022 | Started notice 12 Apr 2024 | |
| Elmbury 25/5966 | 96 | 14 Apr 2026 | Started notice 20 Mar 2026 | |
| Old Course Spaglen Mallow Co.Cork 22/4676 | 96 | 11 Apr 2024 | Started notice 10 Jul 2026 | |
| Gurteenroe Macroom Co.Cork 22/5853 | 96 | 3 Feb 2023 | Started notice 25 Feb 2026 | |
| Janeville Shannonpark Carrigaline Co. Cork 19/5801 | 96 | 20 Dec 2019 | Started notice 5 Oct 2020 | |
| Lisnagar Demesne Rathcormac Co. Cork 18/6579 | 96 | 13 May 2019 | Started notice 18 Feb 2022 | |
| Rath-Beg Abbey-Lands Commons 20/6563 | 95 | 11 Oct 2021 | Started notice 11 Mar 2022 | |
| "Drakes Point" Knocknagore Crosshaven Co. Cork 17/5556 | 95 | 29 Dec 2017 | Started notice 19 Feb 2018 | |
| Carrigane Road Carrigtohill Carrigtwohill Co. Cork 19/4124 | 94 | 13 Feb 2020 | Started notice 11 Nov 2020 | |
| The Miles Road Clonakilty Co. Cork (located west of The Pine 23/20 | 93 | 26 Sept 2023 | Started notice 27 Nov 2023 | |
| Fermoy Townland Fermoy Co Cork 22/4030 | 93 | 13 Aug 2022 | Started notice 2 Jan 2024 | |
| Clashdermot East & Killeagh Gardens Killeagh Co. Cork 17/5741 | 92 | 1 Dec 2017 | Started notice 19 Jun 2021 | |
| Coolfadda Bandon Co. Cork 20/6697 | 85 | 26 Oct 2021 | Started notice 14 Mar 2024 | |
| Janeville Shannonpark Carrigaline Co. Cork 20/4650 | 82 | 15 Mar 2021 | Started notice 20 Mar 2023 | |
| The Miles Clonakilty Co. Cork 18/605 | 81 | 24 Jul 2019 | Started notice 2 Jan 2019 | |
| Inis Alainn Carrignafoy Cobh Co. Cork 19/4376 | 76 | 25 Sept 2019 | Started notice 24 Sept 2024 | |
| Bishop's Island Watergrasshill Co. Cork 22/5878 | 74 | 30 Nov 2022 | Started notice 23 Apr 2024 | |
| Knockgriffin 25/6929 | 73 | 8 Apr 2026 | Started notice 5 Jan 2026 | |
| Kinsale GAA Grounds Bandon Road 22/5657 | 71 | 5 Apr 2023 | Started notice 23 Sept 2026 | |
| The Highlands Ballynaroon Glounthaune County Cork 18/6310 | 70 | 18 Feb 2019 | Started notice 2 May 2019 | |
| Carrigtohill Carrigtwohill Co. Cork 21/5150 | 67 | 20 Jan 2022 | Started notice 5 Aug 2022 | |
| Chickley's Road Sweetfields Youghal Co. Cork 18/4041 | 66 | 19 Oct 2018 | Started notice 8 May 2019 | |
| Knockbrogan Bandon Co. Cork 21/4059 | 65 | 13 Jan 2022 | Started notice 14 Dec 2023 | |
| Baneshane Midleton Co. Cork 17/6604 | 65 | 5 Apr 2018 | Started notice 22 Feb 2023 | |
| Skevanish Innishannon Co. Cork 21/5081 | 64 | 7 Mar 2022 | Started notice 29 Mar 2024 | |
| Inis Álainn Carrignafoy Cobh Co Cork 25/4601 | 63 | 8 Jul 2025 | Started notice 23 Jun 2026 | |
| Cooline Ballyvoloon Cobh Co.Cork 22/5488 | 63 | 12 Jun 2023 | Started notice 24 Jun 2026 | |
| Ballyadam and Carrigtohill Carrigtwohill Co. Cork 21/7130 | 63 | 15 May 2023 | Started notice 8 Feb 2024 | |
| Castlewidenham Castletownroche Co. Cork 19/6554 | 63 | 29 Jan 2021 | Started notice 21 May 2021 | |
| Cregane 21/5969 | 62 | 26 Aug 2022 | Started notice 4 Mar 2024 | |
| Coolmucky Cloughduv Co. Cork 22/4627 | 61 | 10 Oct 2022 | Started notice 31 Aug 2023 | |
| Lisnagar Demense Rathcormac Co. Cork 21/4572 | 61 | 30 Dec 2021 | Started notice 23 Feb 2022 | |
| Kilnagleary Carrigaline Co. Cork 18/5993 | 58 | 17 Jun 2019 | Started notice 22 Jul 2020 | |
| Mill Road and Northern Relief Road 21/6874 | 57 | 14 Jun 2022 | Started notice 19 Apr 2024 | |
| Brindle Hill Rathgoggan South Charleville Co.Cork 22/4578 | 56 | 12 Jan 2023 | Started notice 21 Jul 2023 | |
| Ballyvoloon Cobh Co. Cork 21/5603 | 56 | 7 Dec 2021 | Started notice 21 Mar 2022 | |
| Ryecourt Woods Ryecourt Cloughduv Co. Cork 19/6613 | 56 | 30 Jun 2020 | Started notice 21 Sept 2020 | |
| Coolmucky Cloughduv Co Cork 23/6606 | 52 | 21 Oct 2024 | Started notice 4 Feb 2026 | |
| Ballydaheen Road/ Mill Street Ballydahin Mallow Co. Cork 22/6225 | 52 | 1 Dec 2023 | Started notice 9 Oct 2024 | |
| known as Sisters of Mercy Convent Gortnaclohy Td North Stree 19/565 | 52 | 14 Sept 2020 | Started notice 18 Jun 2020 | |
| Rath-Beg Abbeylands Kinsale Co. Cork 22/6060 | 51 | 10 Mar 2023 | Started notice 10 Apr 2023 | |
| Monadrishane Kilworth Co. Cork 21/4904 | 49 | 8 Sept 2021 | Started notice 3 May 2022 | |
| Milleencoola Bantry Co. Cork 18/561 | 48 | 8 Sept 2021 | Started notice 14 Sept 2018 | |
| Elmbury Carrigtohil Carrigtwohill Co. Cork 22/5005 | 47 | 16 Mar 2023 | Started notice 14 Jun 2023 | |
| Vicars Glebe Glebe Coachford Co. Cork 22/4349 | 45 | 20 Sept 2022 | Started notice 30 Jan 2025 | |
| Distillery Road Moanarone Bandon Co. Cork 21/4711 | 45 | 2 Feb 2022 | Started notice 1 Oct 2024 | |
| Cois Máigh Mogeely Co.Cork 25/5217 | 44 | 19 Dec 2025 | Started notice 10 Feb 2026 |
1–60 of 180Next 60 →
How it is counted
- A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'CORKCO' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| An Coimisiún Pleanála case list | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| Building Control Management System commencement notices | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.
Big developments by name · Where Dublin is building · Sources & freshness