Cork County planning permission: the homes nobody has started
Data updated 6 Nov 2026 · register lag up to 7 days · sources & freshness
11,135 homes in 184 sites of 10 or more have been granted permission in Cork County since 2021. A commencement notice was lodged for 52% of them. 5,270 still have a live permission and no start; 806 of those lapse within a year, and 87 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By local electoral area 10
| Local electoral area | Sites | Homes permitted | Started | Not started | Lapsing | Lapsed |
|---|---|---|---|---|---|---|
| Cobh | 35 | 2,436 | 49% | 1,241 | 332 | 10 |
| Midleton | 40 | 2,804 | 63% | 987 | 56 | 51 |
| Mallow | 10 | 1,065 | 24% | 807 | — | — |
| Bandon - Kinsale | 27 | 1,380 | 50% | 690 | 55 | — |
| Carrigaline | 24 | 1,364 | 49% | 687 | 239 | 12 |
| Fermoy | 16 | 792 | 39% | 480 | 69 | — |
| Macroom | 15 | 478 | 70% | 128 | — | 14 |
| Kanturk | 5 | 231 | 49% | 117 | — | — |
| Bantry-West Cork | 4 | 129 | 23% | 99 | 42 | — |
| Skibbereen-West Cork | 8 | 456 | 93% | 34 | 13 | — |
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2021 | 14 | 625 | 55% | 196 | 87 |
| 2022 | 45 | 1,931 | 62% | 730 | — |
| 2023 | 40 | 2,336 | 79% | 499 | — |
| 2024 | 24 | 1,607 | 64% | 579 | — |
| 2025 | 30 | 1,948 | 32% | 1,324 | — |
| 2026 | 31 | 2,688 | 28% | 1,942 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Permission, no start 86 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Castlepark Castlelands St. Joseph's Road Mallow 24/6036 | 469 | 23 Apr 2025 | Not started lapses in 8 years | Mallow |
| Water-Rock 26/0840 | 452 | 30 Jun 2026 | Not started lapses in 10 years | Cobh |
| Ballynamona 25/5773 | 302 | 24 Feb 2026 | Not started lapses in 4 years | Fermoy |
| Knockgriffin and Water Rock Midleton Co.Cork 21/7264 | 284 | 27 Jan 2023 | Not started lapses within a year | Midleton |
| Coolfadda & Kilbrogan 26/1129 | 240 | 25 Jun 2026 | Not started lapses in 5 years | Bandon - Kinsale |
| Janeville 26/0518 | 229 | 21 Sept 2026 | Not started lapses in 5 years | Carrigaline |
| Spa Glen Mallow Co.Cork 24/4243 | 186 | 10 Oct 2024 | Not started lapses in 3 years | Mallow |
| Courtstown Little Island Co. Cork 24/5328 | 172 | 30 Apr 2025 | Not started lapses in 3 years | Cobh |
| Gortnahomna More Castlemartyr Co.Cork 24/6216 | 150 | 24 Apr 2025 | Not started lapses in 3 years | Midleton |
| Ballinacurra Mill Buildings 26/0282 | 128 | 7 Apr 2026 | Not started lapses in 4 years | Midleton |
| Annabella Mallow Co.Cork 25/5124 | 102 | 4 Nov 2025 | Not started lapses in 4 years | Mallow |
| Carrignafoy Cobh Co Cork 25/5474 | 98 | 23 Mar 2026 | Not started lapses in 4 years | Cobh |
| Janeville Carrigaline Middle Carrigaline Co.cork 22/4809 | 98 | 28 Sept 2022 | Lapsing lapses in 11 months | Carrigaline |
| Janeville Shannonpark Carrigaline Middle 21/5936 | 98 | 17 Nov 2021 | Lapsing lapses within a month | Carrigaline |
| Rathgoggin Middle Charleville Co. Cork 21/4872 | 98 | 11 Oct 2021 | Not started lapses in 4 years | Kanturk |
| Commons West Cloyne Co. Cork 22/6844 | 96 | 26 Jan 2024 | Not started lapses in 2 years | Midleton |
| Ashbourne House Johnstown Glounthaune Co. Cork 21/5072 | 94 | 9 May 2022 | Lapsing lapses in 6 months | Cobh |
| Main Street and lands off Main Street 25/6512 | 79 | 14 Sept 2026 | Not started lapses in 5 years | Midleton |
| Cork Road Knockbrogan Bandon Co. Cork 23/6540 | 77 | 4 Mar 2025 | Not started lapses in 3 years | Bandon - Kinsale |
| Inis Alainn Carrignafoy Cobh Co. Cork 21/5240 | 71 | 4 May 2022 | Lapsing lapses in 6 months | Cobh |
| Coolfadda Bandon Co.Cork 25/5336 | 69 | 29 Jun 2026 | Not started lapses in 5 years | Bandon - Kinsale |
| Courtstown 25/5854 | 67 | 30 Jun 2026 | Not started lapses in 5 years | Cobh |
| Cooline Ballyvoloon Cobh Co. Cork 21/6367 | 65 | 17 May 2022 | Lapsing lapses in 6 months | Cobh |
| Maghereen Kilnagurteen 23/6518 | 62 | 13 Aug 2024 | Not started lapses in 3 years | Macroom |
| Colla Road Skull Skull Co. Cork 24/225 | 57 | 13 May 2025 | Not started lapses in 4 years | Bantry-West Cork |
| Kilnagleary Carrigaline Co. Cork 22/6451 | 51 | 27 Jul 2023 | Not started lapses in 2 years | Carrigaline |
| Brookdale Road Boulaling and Cullen Riverstick Co.Cork 25/5764 | 50 | 3 Dec 2025 | Not started lapses in 4 years | Bandon - Kinsale |
| Knocknagarrane 25/6896 | 44 | 21 Aug 2026 | Not started lapses in 5 years | Bandon - Kinsale |
| Main Street Carrigtohill Carrigtwohill Co.Cork 22/4440 | 43 | 12 Oct 2022 | Lapsing lapses in 11 months | Cobh |
| Mariner's View Maulbaun Passage West Co.Cork 25/5561 | 42 | 31 Oct 2025 | Not started lapses in 4 years | Carrigaline |
| Dromleigh South and Sheskin Bantry Co. Cork. 21/833 | 42 | 12 Sept 2022 | Lapsing lapses in 10 months | Bantry-West Cork |
| Pike Road Rath-Healy Fermoy Co.Cork 22/4863 | 41 | 9 Nov 2022 | Lapsing lapses within a year | Fermoy |
| Turnpike Cross Skaghardgannon Doneraile Co.Cork 23/5819 | 40 | 14 Nov 2024 | Not started lapses in 3 years | Fermoy |
| Kilmoney Carrigaline Co Cork 24/6418 | 39 | 19 Jan 2026 | Not started lapses in 4 years | Carrigaline |
| Station Road Carrigtwohill Carrigtohill 21/6240 | 38 | 21 Jan 2022 | Lapsing lapses in 2 months | Cobh |
| Lakeview Castleredmond Midleton Co.Cork 22/6688 | 35 | 24 Mar 2023 | Not started lapses within a year | Midleton |
| Rath-Beg Abbey-Lands Kinsale Co. Cork 21/6059 | 35 | 1 Jun 2022 | Lapsing lapses in 7 months | Bandon - Kinsale |
| Lakeview Castleredmond Midleton Co.Cork 23/5703 | 34 | 2 Aug 2024 | Not started lapses in 3 years | Midleton |
| Inis Álainn 25/6126 | 33 | 20 Mar 2026 | Not started lapses in 4 years | Cobh |
| Lios Ard Phase 3 Ballyhooly South Ballyhooly Fermoy Co Cork 23/6488 | 33 | 23 Aug 2024 | Not started lapses in 3 years | Fermoy |
| Seafield Business Centre Upper Strand Seafield 22/6699 | 33 | 16 Feb 2024 | Not started lapses in 2 years | Midleton |
| Garrán Ferney Kilnaglery Carrigaline Co Cork 22/5205 | 33 | 4 Nov 2022 | Lapsing lapses within a year | Carrigaline |
| Cappagh Kinsale Co.Cork 24/6120 | 32 | 25 Nov 2025 | Not started lapses in 4 years | Bandon - Kinsale |
| Ashgrove Church Road Aghada Midleton 21/6873 | 31 | 18 Oct 2022 | Lapsing lapses in 11 months | Midleton |
| The Old Course Spaglen Mallow Co. Cork 25/5765 | 28 | 14 Jan 2026 | Not started lapses in 4 years | Mallow |
| Cork Road Coolcarron Fermoy Co. Cork 21/7241 | 28 | 26 Sept 2022 | Lapsing lapses in 11 months | Fermoy |
| Mansfield House Pembroke Passage West Co.Cork 23/5317 | 26 | 18 Apr 2024 | Not started lapses in 2 years | Carrigaline |
| Ballinvarrig 25/6127 | 25 | 2 Jul 2026 | Not started lapses in 5 years | Cobh |
| Knockgriffin Broomfield West Midleton 22/5104 | 25 | 29 Sept 2022 | Lapsing lapses in 11 months | Midleton |
| Coughlan Fuels 26/1114 | 24 | 27 Oct 2026 | Not started lapses in 5 years | Cobh |
| Garrettstown Strand Coolbane Kinsale Co.Cork 23/4236 | 24 | 22 Nov 2023 | Not started lapses in 2 years | Bandon - Kinsale |
| Coolfadda Bandon Co.Cork 22/6426 | 24 | 21 Apr 2023 | Not started lapses within a year | Bandon - Kinsale |
| Emmet Street Mallow Co.Cork 22/4501 | 22 | 5 Dec 2022 | Not started lapses within a year | Mallow |
| The Miles Road Clonakilty Co. Cork (located west of The Piin 25/428 | 21 | 12 Jun 2026 | Not started lapses in 5 years | Skibbereen-West Cork |
| The Cedars Estate Lackenroe Glounthaune Co. Cork 21/6851 | 21 | 6 Oct 2022 | Lapsing lapses in 11 months | Cobh |
| Lower Codrum Macroom Co.Cork 24/6516 | 20 | 19 Jun 2025 | Not started lapses in 4 years | Macroom |
| Watergate Street Knockbrogan Bandon Co.Cork 23/4015 | 20 | 15 Jan 2025 | Not started lapses in 3 years | Bandon - Kinsale |
| Gully Bandon Co. Cork 21/5565 | 20 | 3 May 2022 | Lapsing lapses in 6 months | Bandon - Kinsale |
| Scarteen Lower Newmarket Co Cork 24/4324 | 19 | 28 Mar 2025 | Not started lapses in 3 years | Kanturk |
| Glanduff Kilbrittain Co Cork 24/4139 | 19 | 20 Dec 2024 | Not started lapses in 3 years | Bandon - Kinsale |
1–60 of 86Next 60 →
How it is counted
- A site is one grant of permission for 10 or more homes since 2021: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2021 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'CORKCO' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 6 Nov 2026, 23:00
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC BY 4.0 | 6 Nov 2026, 23:00 | open |
| An Coimisiún Pleanála case list | CC BY 4.0 | 6 Nov 2026, 23:00 | open |
| Building Control Management System commencement notices | CC BY 4.0 | 6 Nov 2026, 23:00 | open |
Recomputed weekly from the store; last built 6 Nov 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.
Big developments by name · Where Dublin is building · Sources & freshness