Permitted, not started · Laois · grants of 10+ homes since 2017

Laois: homes with planning permission that nobody has started

Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness

4,782 homes in 108 sites of 10 or more have been granted permission in Laois since 2017. A commencement notice was lodged for 51% of them. 1,623 still have a live permission and no start; 226 of those lapse within a year, and 689 have already lapsed.

4,782
homes permitted · 108 sites
51%
started · 2,440 homes
1,623
not started · live permission
226
lapse within 12 months
689
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By year granted

Granted inSitesHomesStartedNot startedLapsed
2017159100%0—
20181242066%0144
20191253569%23142
2020928920%17215
20211237552%11367
20221152170%158—
20231368244%258121
20241160857%263—
20251780945%441—
20261048421%350—

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 30 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 86% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Bircrest Limited854329%30479
The Maltings & Granary Limited728547%151—
Whitehorse Developments TA Capital Homes21070%107—
JC Brenco Developments Limited1980%98—
Dargan Woods Devco Limited211423%88—
Tullyagan Residential Limited1860%86—
Whitehorse Developments Limited T and A Capital Homes Limited1820%82—
Hebron Mooncoin Limited1710%71—
Werdna Limited1580%58—
A-Rated New Homes Limited1440%44—
David Walsh Homes Limited524883%42—
Kingscroft Developments Limited417879%38—
Brook Advantage Limited26356%28—
Cubic Housing Limited410675%26—
M&M Prime Holdings Limited1260%26—
Graham Developments1230%23—
Vesta Construction1180%18—
Twomilehouse Construction Limited25871%17—
Superior Formwork Limited25470%16—
Ardain Developments Limited1140%14—
Furey Consulting Engineers Limited1140%14—
Solus Developments Limited1110%11—
Nyquist Property Limited2200%1010
Salzagold Limited1210100%0—
Marina Quarter Limited1175100%0—
Boderg Developments Limited11210%0121
Aston Homes Limited310991%010
Randelswood Holdings Limited197100%0—
Thomas Kelly & Sons Group comprising O'Ceallaigh Westfield Limited&Thomas Kelly & Sons Limited195100%0—
Alder Residential Limited179100%0—

Work started 50 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Graiguecullen 2188721024 Jan 2024Started notice 1 Aug 2026
Dublin Road 23603661751 Nov 2023Started notice 24 Apr 2024
Meadows Fort 25602419818 Sept 2025Started notice 31 Aug 2026
Meadows Fort 2560210989 Sept 2025Started notice 27 Oct 2025
Bishopswood Road 25602559711 Sept 2025Started notice 1 Aug 2026
Rathevan 214969516 Mar 2022Started notice 26 Jan 2026
Portlaoise 25603859224 Feb 2026Started notice 7 May 2026
Summerhill Lane 173968714 Jun 2018Started notice 7 Sept 2018
Killenard 216437916 Feb 2022Started notice 18 Aug 2022
Church Avenue 183017214 Jan 2019Started notice 26 Aug 2021
Cushina Road/Edenderry Road R419 19174716 Nov 2019Started notice 11 Aug 2023
Portlaoise 2360348687 May 2024Started notice 2 Sept 2024
Grattan Street 205836729 Nov 2021Started notice 8 Oct 2024
part of former Minch Norton Maltings 2164662 Nov 2021Started notice 17 Jun 2022
Clonroosk at Clonroosk Abbey 172226631 Jan 2018Started notice 1 Oct 2018
Meadows Way 225546215 Dec 2022Started notice 3 Jan 2023
Cooltederry 18422621 May 2019Started notice 15 Jun 2021
Heathfield Ballymooney 171405925 Sept 2017Started notice 27 Feb 2019
Ballycullenbeg 2165225 Jan 2022Started notice 23 Apr 2024
Bishopswood Road 24604604911 Aug 2025Started notice 18 Apr 2026
Townparks 22439498 May 2023Started notice 7 Dec 2023
Harpurs Lane 195804515 Jun 2020Started notice 28 Apr 2021
Kilminchy 18363419 Jul 2019Started notice 17 Oct 2022
Harpur's Lane 191514021 Aug 2019Started notice 20 Jul 2021
Rush Hall 16488384 Jan 2018Started notice 15 Sept 2021
Dublin Road 191443611 Jun 2019Started notice 30 Jan 2020
Borris Great Borris Road 177113612 Nov 2018Started notice 6 Aug 2019
Borris Road in the townland of 24601563515 Jul 2024Started notice 2 Aug 2024
Mountmellick Road 196703417 Jun 2021Started notice 22 Apr 2024
Kilminchy 21561316 May 2022Started notice 23 Apr 2024
Harpur's Lane 222712828 Mar 2023Started notice 12 May 2024
Dargan Woods 2560311268 Dec 2025Started notice 12 May 2026
Droughill 19320266 Nov 2019Started notice 27 Nov 2020
106-129 The Glen 214192411 Jan 2022Started notice 31 Jul 2026
Ballyroan 18722330 Aug 2018Started notice 12 Aug 2019
Derryounce 225642110 Jul 2023Started notice 31 Jul 2023
Shannon Street 218462027 Sept 2022Started notice 21 Aug 2023
Main Street 22921923 Jan 2023Started notice 6 Nov 2023
Located off Market Sq & French Church St. 20346182 Jun 2021Started notice 20 Sept 2021
Main Street 174031631 Jan 2018Started notice 2 Jan 2019
Ballyroan 25604861226 Jan 2026Started notice 10 Feb 2026
Rockview 2460062127 May 2024Started notice 5 Sept 2024
Clonroosk Abbey 19660125 Mar 2020Started notice 11 Dec 2020
Aghnaharna 18546123 Oct 2019Started notice 6 May 2021
Shannon Street & Wallis Street 221601120 Feb 2023Started notice 23 Aug 2023
Meadows Way 2460066107 May 2024Started notice 24 Jun 2024
Ard Branagh 23605341021 Mar 2024Started notice 22 Apr 2024
Carmallagh 21561014 Sept 2021Started notice 7 Mar 2023
Killeshin 19111011 Nov 2019Started notice 24 Feb 2020
Lake Drive 176901023 Nov 2018Started notice 26 Aug 2019

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'LAOIS' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC-BY-4.019 Sept 2026, 07:05open
An Coimisiún Pleanála case listCC-BY-4.019 Sept 2026, 07:05open
Building Control Management System commencement noticesCC-BY-4.019 Sept 2026, 07:05open

Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.

Big developments by name · Where Dublin is building · Sources & freshness