Meath planning permission: the homes nobody has started
Data updated 6 Nov 2026 · register lag up to 7 days · sources & freshness
11,650 homes in 178 sites of 10 or more have been granted permission in Meath since 2021. A commencement notice was lodged for 56% of them. 4,333 still have a live permission and no start; 266 of those lapse within a year, and 87 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By local electoral area 6
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2021 | 8 | 525 | 62% | 201 | — |
| 2022 | 38 | 1,283 | 76% | 110 | 13 |
| 2023 | 27 | 1,399 | 87% | 142 | 35 |
| 2024 | 35 | 1,912 | 91% | 164 | 13 |
| 2025 | 39 | 3,415 | 42% | 1,958 | 26 |
| 2026 | 31 | 3,116 | 28% | 1,758 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 30 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 67% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| John Connaughton Limited | 1 | 810 | 0% | 810 | — |
| Beo Properties Limited | 1 | 364 | 0% | 364 | — |
| Kingscroft Developments Limited | 2 | 251 | 0% | 251 | — |
| Azra Property Company Limited | 2 | 420 | 50% | 211 | — |
| Rockmill Limited | 1 | 201 | 0% | 201 | — |
| Carroll Estates Dunboyne Limited | 1 | 171 | 0% | 171 | — |
| The Academy Street Partnership | 1 | 95 | 0% | 95 | — |
| Apolloseven Investments Limited | 2 | 111 | 36% | 71 | — |
| Carroll Estates (Dublin) Limited | 2 | 113 | 50% | 56 | — |
| Leinster Land Developments Limited | 1 | 43 | 0% | 43 | — |
| Indus Properties Limited | 1 | 37 | 0% | 37 | — |
| Pavement Homes Limited | 1 | 36 | 0% | 36 | — |
| Poplock Limited | 1 | 36 | 0% | 36 | — |
| Danceglen Limited T | 1 | 30 | 0% | 30 | — |
| Sasula Unlimted Company | 1 | 25 | 0% | 25 | — |
| Minson Property Limited | 1 | 24 | 0% | 24 | — |
| Sasula Unlimited Company | 4 | 59 | 76% | 14 | — |
| Rocktop Asset Management Limited | 1 | 14 | 0% | 14 | — |
| Cosgrove Properties Limited | 1 | 13 | 0% | 13 | — |
| Bluehume Limited | 2 | 23 | 48% | 12 | — |
| Leonard Price Developments Limited | 1 | 10 | 0% | 10 | — |
| Laurem Construction Limited | 1 | 10 | 0% | 10 | — |
| KADA Limited | 1 | 10 | 0% | 10 | — |
| Marina Quarter Limited | 3 | 502 | 100% | 0 | — |
| Albert Developments Limited | 2 | 420 | 100% | 0 | — |
| Glenveagh Homes Limited | 8 | 373 | 67% | 0 | — |
| Cairn Homes Properties Limited | 4 | 282 | 100% | 0 | — |
| Marina Quarter Limited. N | 1 | 256 | 100% | 0 | — |
| Hayfield Homes Limited | 3 | 231 | 100% | 0 | — |
| Manley Developments Limited | 4 | 225 | 100% | 0 | — |
Permission, no start 47 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Station Road and Old Navan Road 2460709 | 810 | 27 Aug 2025 | Not started lapses in 9 years | Dunboyne |
| Ratoath 2560637 | 364 | 14 Aug 2025 | Not started lapses in 4 years | Ratoath |
| Principally located in Bennetstown 2660001 | 356 | 21 Sept 2026 | Not started lapses in 5 years | Dunboyne |
| Dunboyne 2660481 | 314 | 6 Aug 2026 | Not started lapses in 8 years | Dunboyne |
| Academy Street 2660748 | 245 | 23 Sept 2026 | Not started lapses in 4 years | Navan |
| Jamestown 2660045 | 240 | 16 Apr 2026 | Not started lapses in 4 years | Ratoath |
| lands generally bound 2560854 | 211 | 21 Nov 2025 | Not started lapses in 7 years | Ratoath |
| Old Navan Road 2460625 | 171 | 27 Mar 2025 | Not started lapses in 3 years | Dunboyne |
| Main Street R125 Ballybin Road 2561104 | 130 | 27 Jan 2026 | Not started lapses in 4 years | Ratoath |
| An Existing Creche Building at Robinrath Drive 2660662 | 97 | 30 Sept 2026 | Not started lapses in 5 years | Commons |
| Academy Street/Circular Road/Bridge Street 221421 | 95 | 14 Sept 2023 | Not started lapses in 2 years | Navan |
| Boyne Road 2660256 | 93 | 16 Sept 2026 | Not started lapses in 2 years | Athlumney Bridge |
| Boyne Road 2660717 | 93 | 16 Sept 2026 | Not started lapses in 2 years | Athlumney Bridge |
| Baltrasna 2561359 | 71 | 7 May 2026 | Not started lapses in 4 years | 9 Mile Stone |
| 10 The Oakwood 2560440 | 65 | 7 Aug 2025 | Not started lapses in 5 years | Ratoath |
| Bunboggan 24204 | 64 | 4 Mar 2025 | Not started lapses in 3 years | Athboy |
| Mahir House 2460684 | 63 | 18 Jun 2025 | Not started lapses in 4 years | 9 Mile Stone |
| Site B Mornington 23885 | 56 | 17 Sept 2024 | Not started lapses in 3 years | Laytown Bettystown-Lea-7 |
| Charterschooland and Manorlands 2nd Division 2660278 | 43 | 15 Jun 2026 | Not started lapses in 5 years | Wellington Place |
| Joe Molloy’s Bookmakers . 2460197 | 37 | 26 Nov 2024 | Not started lapses in 3 years | Clonee |
| Bridge Street and Bachelors Walk 2560600 | 36 | 22 Sept 2025 | Not started lapses in 4 years | Ashbourne |
| Clonee House 2460410 | 36 | 27 Mar 2025 | Not started lapses in 3 years | Clonee |
| Johnstown 2560210 | 28 | 28 Nov 2025 | Not started lapses in 4 years | Ratoath |
| Dunsany 2561346 | 25 | 26 Mar 2026 | Not started lapses in 4 years | Ratoath |
| Johnstown 221640 | 24 | 19 May 2023 | Not started lapses in 3 years | Alexander Reid |
| Bridge St & The Banba Hall 22219 | 23 | 7 Dec 2022 | Not started lapses within a year | Navan |
| Knockboyne House 2460943 | 22 | 17 Dec 2025 | Not started lapses in 4 years | Navan |
| Creevagh 2461110 | 22 | 3 Jul 2025 | Not started lapses in 4 years | Laytown Bettystown-Lea-7 |
| Commons 24440 | 15 | 22 Jan 2026 | Not started lapses in 4 years | Laytown Bettystown-Lea-7 |
| Town Parks & Fostersfields 2460241 | 15 | 29 May 2025 | Not started lapses in 4 years | Athboy |
| Hunters Yard 2560256 | 14 | 18 Sept 2025 | Not started lapses in 5 years | Ratoath |
| Greenane 2460325 | 14 | 7 Feb 2025 | Not started lapses in 4 years | Dunshaughlin |
| 8 THE PADDOCKS KILLEEN CASTLE DEMESNE 2660814 | 13 | 30 Sept 2026 | Not started lapses in 2 years | Ratoath |
| 2 The Paddocks Killeen Castle 2560702 | 13 | 17 Oct 2025 | Not started lapses in 4 years | Ratoath |
| 4 The Paddocks 2460350 | 13 | 31 Oct 2024 | Not started lapses in 3 years | Ratoath |
| 6 The Paddocks 2460583 | 13 | 31 Oct 2024 | Not started lapses in 3 years | Ratoath |
| 5 The Paddocks Killeen Castle Demesne 2360510 | 13 | 31 Oct 2024 | Not started lapses in 3 years | Ratoath |
| 12 The Paddocks 23159 | 13 | 23 May 2023 | Not started lapses in 2 years | Ratoath |
| Main Street 2660023 | 12 | 2 Nov 2026 | Not started lapses in 5 years | Duleek |
| Emmet Street 221176 | 12 | 27 Oct 2022 | Not started lapses in 2 years | Wellington Place |
| Donaghmore 2660379 | 11 | 9 Oct 2026 | Not started lapses in 5 years | Donaghmore |
| Carrickmacross Road 2460435 | 11 | 8 Aug 2024 | Not started lapses in 4 years | Kells |
| Kilcarn 2457 | 11 | 23 May 2024 | Not started lapses in 2 years | Kilcarn |
| Carlanstown 2560711 | 10 | 17 Oct 2025 | Not started lapses in 4 years | Kells |
| Smithstown 2460699 | 10 | 19 Dec 2024 | Not started lapses in 4 years | Julianstown |
| Glebe T.d. 23590 | 10 | 28 Jul 2023 | Not started lapses in 3 years | Trim |
| Kilmainhamwood Retirement Village 22325 | 10 | 26 Oct 2022 | Not started lapses in 2 years | Kells |
How it is counted
- A site is one grant of permission for 10 or more homes since 2021: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2021 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'MEATH' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 6 Nov 2026, 23:00
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC BY 4.0 | 6 Nov 2026, 23:00 | open |
| An Coimisiún Pleanála case list | CC BY 4.0 | 6 Nov 2026, 23:00 | open |
| Building Control Management System commencement notices | CC BY 4.0 | 6 Nov 2026, 23:00 | open |
Recomputed weekly from the store; last built 6 Nov 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.