Offaly: homes with planning permission that nobody has started
Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness
2,449 homes in 53 sites of 10 or more have been granted permission in Offaly since 2017. A commencement notice was lodged for 49% of them. 929 still have a live permission and no start; 142 of those lapse within a year, and 308 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2018 | 2 | 217 | 100% | 0 | — |
| 2019 | 5 | 284 | 67% | 0 | 94 |
| 2020 | 5 | 191 | 80% | 0 | 39 |
| 2021 | 8 | 260 | 35% | 78 | 90 |
| 2022 | 8 | 220 | 41% | 44 | 85 |
| 2023 | 10 | 362 | 46% | 196 | — |
| 2024 | 4 | 338 | 57% | 146 | — |
| 2025 | 6 | 302 | 0% | 302 | — |
| 2026 | 5 | 275 | 33% | 163 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 28 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 95% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| Arden Square Development Limited | 2 | 196 | 0% | 196 | — |
| Tullamore Vita Stilo Limited and a Capital Homes | 3 | 200 | 0% | 182 | 18 |
| JAMES SPOLLEN LIMITED | 1 | 95 | 0% | 95 | — |
| RIVERPOINT CONSTRUCTION LIMITED | 1 | 78 | 0% | 78 | — |
| Beech Avenue Properties Limited | 2 | 119 | 51% | 58 | — |
| Collins Lane Housing Development Limited | 3 | 150 | 68% | 48 | — |
| Offaly Solar Energy AS Limited | 1 | 48 | 0% | 48 | — |
| Fitzpatrick & Heavey Homes Limited | 2 | 79 | 51% | 39 | — |
| SOPHIA HOUSING ASSOCIATION CLG | 1 | 28 | 0% | 28 | — |
| LEAMORE CONSTRUCTION LIMITED | 1 | 25 | 0% | 25 | — |
| JOHN FLANAGAN DEVELOPMENTS Limited | 3 | 135 | 67% | 19 | 26 |
| SPA ROAD HOMES LIMITED | 1 | 19 | 0% | 19 | — |
| RAVINE Limited | 1 | 18 | 0% | 18 | — |
| MONROE STREET DEVELOPMENTS LIMITED | 1 | 10 | 0% | 10 | — |
| CODD PROPERTY HOLDINGS LIMITED | 6 | 429 | 68% | 0 | 139 |
| Newlyn Homes Limited | 3 | 225 | 81% | 0 | 43 |
| TULLAMORE VITA STILO Limited T and A CAPITAL HOMES | 1 | 99 | 100% | 0 | — |
| FERNSIDE HOMES Limited | 1 | 75 | 100% | 0 | — |
| DAINGEAN ROAD RESIDENTIAL LIMITED | 1 | 62 | 100% | 0 | — |
| GLENVEAGH HOMES Limited | 2 | 40 | 75% | 0 | 10 |
| SMART 2 MANAGEMENT VENTURES LIMITED | 1 | 39 | 0% | 0 | 39 |
| SAMLEIGH PROPERTIES Limited | 2 | 37 | 100% | 0 | — |
| LIAM WALSH & COMPANY LIMITED | 2 | 34 | 100% | 0 | — |
| PMB CONSTRUCTION Limited | 1 | 22 | 0% | 0 | 22 |
| N.C.E. DEVELOPMENTS Limited | 1 | 21 | 100% | 0 | — |
| GREYPOST DEVELOPMENTS LIMITED | 1 | 18 | 100% | 0 | — |
| BROUDER BROS STEEL LIMITED | 1 | 16 | 100% | 0 | — |
| ROBIN INVESTMENTS FR. MCWEY STREET EDENDERRY Limited | 1 | 11 | 0% | 0 | 11 |
Work started 22 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| EISCIR MEADOWS/NORBURY WOODS 17231 | 201 | 29 May 2018 | Started notice 4 Jan 2019 | |
| Collins Lane 2360059 | 102 | 12 Feb 2024 | Started notice 29 Nov 2024 | |
| CLARA ROAD 1939 | 99 | 19 Jul 2019 | Started notice 22 Jul 2020 | |
| Father Paul Murphy Street 2560550 | 92 | 20 Apr 2026 | Started notice 17 Jun 2026 | |
| TYRELLS ROAD ARDAN / PUTTAGHAN TULLAMORE 23216 | 90 | 26 Jan 2024 | Started notice 31 Dec 2024 | |
| TYRRELLS BROOK 19136 | 90 | 12 Nov 2020 | Started notice 1 Apr 2022 | |
| ST. MARY'S ROAD 18266 | 75 | 28 Jun 2019 | Started notice 30 Oct 2019 | |
| DAINGEAN ROAD 22523 | 62 | 3 Oct 2023 | Started notice 16 Apr 2024 | |
| SEFFIN AND SCURRAGH 1778 | 61 | 15 Sept 2022 | Started notice 9 May 2018 | |
| EISCIR MEADOWS/ NORBURY WOODS ARDAN 21137 | 45 | 24 Aug 2021 | Started notice 4 Oct 2022 | |
| EISCIR MEADOWS/NORBURY WOODS 2334 | 44 | 23 Aug 2023 | Started notice 15 Sept 2023 | |
| FOREST VIEW 22274 | 40 | 26 Oct 2023 | Started notice 19 Apr 2024 | |
| C. 1.8 HECTARES BOUNDED GENERALLY BY "EISCIR MEADOWS" 20465 | 30 | 18 Feb 2021 | Started notice 18 Mar 2021 | |
| BALLYDOWNAN 19210 | 23 | 8 Jan 2020 | Started notice 1 Sept 2022 | |
| ARD NA CARRAIGE 19391 | 21 | 18 Feb 2020 | Started notice 19 Apr 2022 | |
| BALLYVORA 22198 | 20 | 3 May 2023 | Started notice 10 Apr 2024 | |
| FATHER MCWEY STREET EDENDERRY 21297 | 18 | 25 Feb 2022 | Started notice 26 Dec 2024 | |
| MCAULEY DRIVE 19282 | 18 | 2 Jun 2020 | Started notice 1 Sept 2021 | |
| BALLYVORA 21396 | 17 | 28 Sept 2021 | Started notice 31 Jul 2023 | |
| MCAULEY DRIVE 18235 | 16 | 8 Feb 2019 | Started notice 7 Apr 2021 | |
| BEECHGROVE 17491 | 16 | 24 Jul 2018 | Started notice 17 Jun 2019 | |
| BALLINCUR 21131 | 12 | 28 Jan 2022 | Started notice 7 Dec 2022 |
How it is counted
- A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'OFFALY' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| An Coimisiún Pleanála case list | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| Building Control Management System commencement notices | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.