Approved in Jun 2022. Built and signed off.

  1. 17 Dec 2021Received
  2. 25 May 2022Conditional
  3. 30 Jun 2022Final approval
  4. 15 Jul 2022Building started
  5. 6 Jul 2023Signed off
Status
Building started
Decision
Conditional · 25 May 2022
Council
Kildare County Council
Type
PERMISSION
Site
4.78 ha

What’s proposed

works to the existing Murphy International Limited Headquarters to accommodate two new industrial buildings, comprising a Steel Fabrication building and a Pipe Ancillary building, and associated development and works. The Steel Fabrication Building of 2,495 sqm is 13.1 metres in height and accommodates a fabrication area of 2,229 sqm and a staff welfare area of 133 sqm at ground floor level, and an ancillary office of 133 sqm at first floor level. The Pipe Ancillary Building of 760 sqm is single storey and 9.3 metres in height, and will accommodate workshops. Solar photovoltaic panels are proposed on the roofs of both buildings. It is proposed to demolish 4 No. existing buildings including an Office (300sqm), Lean-to Warehouse (240 sqm), Warehouse (415 sqm), and a Storage Barn (112 sqm), and to demolish the existing boundary walls on Great Connell Road and on part of the existing access road. It is proposed to upgrade the existing access road to provide a 7.5 metre carriageway, 1.5 metre grass verge, 2 metre cycle lane, 2 metre footpaths, tree planting and a 2.5 metre boundary wall to the subject site, and to upgrade the boundary on Great Connell Road by removing the existing entrances and providing a 1.5 metre grass verge, 2 metre cycle lane, 2 metre foot path, tree planting and a 2.5 metre acoustic timber fence. It is proposed to provide 84 No. car parking spaces and 33 No. bike parking spaces, 3 No. signs of 5.2 sqm each are proposed; 1 No. on the southwest elevation of the Steel Fabrication Building, 1 No. on the northeast elevation of the Pipe Ancillary Building, and 1 No. on the northwest elevation of the Pipe Ancillary Building. The existing yard will be extended by 0.9 ha. These and all ancillary works including the regrading of an existing drainage ditch, all water infrastructure, internal roads, and landscaping are proposed on a site of 4.7 ha

Planning details

Reference
211780
Local authority
Kildare County Council
Status
Commenced · register status “APPLICATION FINALISED”
Received
17 Dec 2021
Decision due
26 May 2022 · decided 25 May 2022
Decision
Conditional on 25 May 2022
Site area
4.78 ha from the mapped boundary, not the council's figure

Live near Great Connell?

Everything else planned on your street, in one report.

Check my street
Council register ↗

Nearby 8 · 500 m · 12 months

Distance
Time

Explore this area on the map →

Homes nearby

Building started

  • 15 Jul 2022 · Builder told the council work was starting (seven-day notice) SN0007426KE
  • 15 Jul 2022 · Builder told the council work was starting (seven-day notice) SN0007427KE

Zoning

C6 — Waterfront

Zoned for waterfront and harbour-related development.

Where this comes from

National planning feed (NPAD), fetched 11 Sept 2026, 18:51.

Source: National Planning Application Database · fetched 11 Sept 2026, 18:51
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.011 Sept 2026, 18:51open
Summary

211780 is a planning application to Kildare County Council for works to the existing Murphy International Limited Headquarters to accommodate two new, received on 17 Dec 2021; permission was granted with conditions on 25 May 2022.