- A c. 0.078 Ha site at Nos. 32-35 Pearse Street, Dublin 2 (all Protected Structures)., The site is generally bound to the south by Pearse Street, and to the north by Brunswick Villas, Dublin 2. Registered Application
PROTECTED STRUCTURE: Esprit Investments Limited intend to apply for permission for development at this c. 0.078 Ha site at Nos. 32-35 Pearse Street, Dublin 2 (all Protected Structures). The site is generally bound to the south by Pearse Street and to the north by Brunswick Villas, Dublin 2.
The proposed development, which will provide a total of 21 No. residential units (4 No. 2-bed apartments within Nos. 32-35 Pearse Street and 17 No. apartments (4 No. studios; 11 No. 1-bed units; and 2 No. 2-bed units) within a new residential building), will principally consist of the demolition (628 sq m) of all existing structures to the rear of Nos. 32-35 Pearse Street and the construction of a new part-6 to part-7 storey residential building (1,204 sq m).
The development will also include: restoration, repair and internal modification of Nos. 32, 33, 34 and 35 Pearse Street; the change of use of the ground floor level of No. 33 Pearse Street from office to retail (49 sq m) and the first and second floor levels from office to residential (106 sq m); the change of use of the first floor level of No. 34 Pearse Street from retail to residential (53 sq m) and the second floor level from office to residential (53 sq m); the change of use of the first and second floor levels of No. 35 Pearse Street from office to residential (100 sq m); and the provision a single-storey extension to the rear of No. 32 Pearse Street (78 sq m).
The existing/permitted uses at ground floor levels of No. 32 Pearse Street (a café/restaurant), No. 34 Pearse Street (retail) and No. 35 Pearse Street (retail) will remain unchanged. The existing uses at first and second floor levels of No. 32 Pearse Street (a residential unit) will also remain unchanged.
The development will also include: elevational works to Nos. 32-35 Pearse Street, comprising the repair, cleaning and repointing of the brickwork; the removal of non-original render to the rear elevations of Nos. 33 and 35; the reinstatement of multi-pane sash windows to the rear elevations of Nos. 32-35 Pearse Street; hard and soft landscaping; bicycle parking; blue/green roofs; bin storage; plant; gates; and all associated site development works above and below ground.
WEB2894/26received 30 Jul 2026492 m away
- 21 Westland Row, The University College of Dublin, Dublin 2 Registered Application
PROTECTED STRUCTURE: The construction of a new external access ramp and associated works to improve access to the existing front door at No 21 Westland Row, the University of Dublin Trinity College, Dublin 2. The proposed development is within the curtilage of a Protected Structure.
WEB2883/26received 29 Jul 2026495 m away
- Citigroup Building, 1 North Wall Quay, Dublin 1, D01 T8Y1. The site is bound by North Wall Quay to the south, Commons Street to the west, Clarion Quay/Alderman Way to the north and an access ramp to the existing basement to the east. D01 T8Y1 Registered Application
We, NWQ Devco Limited, intend to apply for a 10 year planning permission for development at a site consisting of the CitiGroup Building, 1 North Wall Quay, Dublin 1, D01 T8Y1. The site is bound by North Wall Quay to the south, Commons Street to the west, Clarion Quay/Alderman Way to the north and an access ramp to the existing basement to the east. The site area is c. 0.88 ha.
The proposed development will consist of:
• Partial demolition, removal of existing facades and extension of existing 5-6 storeys office building;
• The resulting proposed extended development (c. 60,119 sq.m) ranges in height from 6 no. to 12 no. storeys in height over existing basement comprising office accommodation, 2 no. hotels, a retail/café unit and a community space;
• The proposed development comprises 4 no. blocks:
o Block A (6-11 storeys) comprises office accommodation.
o Block B (12 no. storeys) comprises office accommodation.
o Block C (10 storeys) will comprise a hotel with 201 no. bedrooms;
o Block D (6-7 storeys) will comprise a hotel with 135 no. bedrooms;
o It is noted that there will be a change of use of part of the existing retained floor area from office to hotel (c. 12,847 sqm) to accommodate the proposed hotels.
• 1 no. retail/cafe unit (91 sq.m) is provided within Block D at ground floor level;
• 1 no. internal community space (654 sq.m) is provided at ground floor level;
• A shared entrance for Blocks C and D;
• Provision of a shared atrium between Block C and Block D;
• Outdoor terraces at 5th, 6th, 7th, 9th, and 11th floor levels;
• Green roofs and blue roofs are provided across the scheme;
• 32 no. car parking spaces will be provided at basement level to serve the development. This represents a reduction of 132 no. car parking spaces in comparison to the existing office building on the site;
• 456 no. bicycle spaces (inc. and 4 no. motorcycle spaces are proposed at basement level;
• 18 no. short-stay bicycle space (9 no. Sheffield stands) are proposed at surface level;
• The development includes the fill and cover of existing access ramp to existing basement to provide a landscaped community pocket park (244 sq.m) to the east of the building. The park will include a pedestrian link from North Wall Quay to Clarion Quay;
• Provision of upgrades to existing public realm within application site including public footpaths along North Wall Quay, Commons Street and Clarion Quay;
• All ancillary and associated works to facilitate the development including plant, pv panels, switch rooms, generators, water tanks, sprinkler plant, ESB substations, landscaping, telecommunications infrastructure and utilities connections and infrastructure.
An Environmental Impact Assessment Report and Natura Impact Statement have been prepared in respect of the proposed development and have been submitted with the planning application.
WEB2850/26received 24 Jul 2026206 m away
- 19-20 Lombard Street East, and 112-113 & 114 Townsend Street, Dublin 2 Registered Application
We, ORHRE Management Services Limited, intend to apply for permission for development at this site at 19-20 Lombard Street East and 112-113 & 114 Townsend Street, Dublin 2. The proposals comprise amendments to planning permission DCC Reg. Ref.: WEB2350/25.
The development will consist of the demolition of existing vacant two storey building (c. 173 sqm) at the southern perimeter of the site and the construction of a 5 storey (16.2 metres above ground level) extension (c. 300 sqm) of the permitted hostel development providing an additional 8 no. bedrooms (105 no. in total) at upper floors, publicly accessible café (c. 67 sqm) fronting Lombard Street (with external seating area and 2 no. visitor bicycle parking spaces), ESB substation, meter room, bike store and fire escape (accessed from the western elevation) at ground floor level, reconfiguration of layouts at basement to sixth floor level (additional 56 sqm), associated elevational changes to the southern, eastern and western elevations to provide additional and reconfigured windows, and material finishes, relocation of permitted signage area 01 from southern elevation to eastern elevation above café at ground floor level, green roof and plant (first floor roof level), minor amendments to roof level at sixth floor arising from fire certification and all associated works to facilitate the development.
WEB2846/26received 24 Jul 2026233 m away
- Citigroup Building, 1 North Wall Quay, Dublin 1, D01 T8Y1 The site is bound by North Wall Quay to the South, Commons Street to the West, Clarion Quay/Alderman Way to the North and an access ramp to the existing basement to the East., D01 T8Y1 Application declared invalid
We, NWQ Devco Limited, intend to apply for a 10 year planning permission for development at a site consisting of the CitiGroup Building, 1 North Wall Quay, Dublin 1, D01 T8Y1. The site is bound by North Wall Quay to the south, Commons Street to the west, Clarion Quay/Alderman Way to the north and an access ramp to the existing basement to the east. The site area is c. 0.88 ha.
The proposed development will consist of:
• Partial demolition, removal of existing facades and extension of existing 5-6 storeys office building;
• The resulting proposed extended development (c. 60,119 sq.m) ranges in height from 6 no. to 12 no. storeys in height over existing basement comprising office accommodation, 2 no. hotels, a retail/café unit and a community space;
• The proposed development comprises 4 no. blocks:
o Block A (6-11 storeys) comprises office accommodation.
o Block B (12 no. storeys) comprises office accommodation.
o Block C (10 storeys) comprises a hotel with 201 no. bedrooms.
o Block D (6-7 storeys) comprises a hotel with 135 no. bedrooms.
• 1 no. retail/cafe unit (91 sq.m) is provided within Block D at ground floor level;
• 1 no. internal community space (654 sq.m) is provided at ground floor level;
• A shared entrance for Blocks C and D;
• Provision of a shared atrium between Block C and Block D;
• Outdoor terraces at 5th, 6th, 7th 9th, and 11th floor levels;
• Green roofs and blue roofs are provided across the scheme;
• 32 no. car parking spaces will be provided at basement level to serve the development. This represents a reduction of 132 no. car parking spaces in comparison to the existing office building on the site;
• 456 no. bicycle spaces (inc. and 4 no. motorcycle spaces are proposed at basement level;
• 18 no. short-stay bicycle space (9 no. Sheffield stands) are proposed at surface level;
• The development includes the fill and cover of existing access ramp to existing basement to provide a landscaped community pocket park (244 sq.m) to the east of the building. The park will include a pedestrian link from North Wall Quay to Clarion Quay;
• Provision of upgrades to existing public realm within application site including public footpaths along North Wall Quay, Commons Street and Clarion Quay;
• All ancillary and associated works to facilitate the development including plant, pv panels, switch rooms, generators, water tanks, sprinkler plant, ESB substations, landscaping, telecommunications infrastructure and utilities connections and infrastructure.
An Environmental Impact Assessment Report and Natura Impact Statement have been prepared in respect of the
proposed development and have been submitted with the planning application.
WEB2791/26received 20 Jul 2026decided 23 Jul 2026206 m away
- 21 Westland Row, The University Of Dublin Trinity College, Westland Row, Dublin 2 Application declared invalid
PROTECTED STRUCTURE: The construction of a new external access ramp and associated works to improve access to the existing front door at No 21 Westland Row, the University of Dublin Trinity College, Dublin 2. The proposed development is within the curtilage of a Protected Structure.
WEB2712/26received 9 Jul 2026decided 14 Jul 2026495 m away
- 81B Campshires, Sir John Rogerson’s Quay, Dublin 2, D02 NW20 Registered Application
RETENTION: Retention permission for:
(i) change of use of existing building to provide office space (789sq.m) at ground and first floor levels and a café/restaurant (76sq.m) in the western portion of the ground floor level;
(ii) internal office fit out at ground and first floor levels including the provision of stair and lift cores, meeting rooms/meeting pods, bathroom facilities, a staff canteen, reception area, storage space and plant rooms;
(iii) internal café fit out in the western portion of the ground floor level including the provision of counters, preparation and kitchen areas, a staff W.C and staff lockers, storage; and
(iv) all associated ancillary works.
This application relates to a development within the North Lotts and Grand Canal Dock Strategic Development Zone Planning Scheme area.
WEBDSDZ2555/26received 23 Jun 2026129 m away
- 81B Campshires, Sir John Rogerson’s Quay, Dublin 2, D02 NW20 Application declared invalid
RETENTION:Retention permission for:
(i) change of use of existing building to provide office space (789sq.m) at ground and first floor levels and a café/restaurant (76sq.m) in the western portion of the ground floor level;
(ii) internal office fit out at ground and first floor levels including the provision of stair and lift cores, meeting rooms/meeting pods, bathroom facilities, a staff canteen, reception area, storage space and plant rooms;
(iii) internal café fit out in the western portion of the ground floor level including the provision of counters, preparation and kitchen areas, a staff W.C and staff lockers, storage; and
(iv) all associated ancillary works.
This application relates to a development within the North Lotts and Grand Canal Dock Strategic Development Zone Planning Scheme area.
WEBDSDZ2534/26received 19 Jun 2026decided 22 Jun 2026129 m away
- Pret A Manger, Pearse Street Station, Westland Row, Dublin 2, Ireland, D02 RV00 Registered Application
PROTECTED STRUCTURE: RETENTION: Carebrook Partnership Ltd. is applying to Dublin City Council for retention permission for illuminated signage advertising Pret A Manger café outlet to the north-west (front façade) of the building including two internally illuminated roundal signs on two doors and two internally illuminated projecting signs on the brick facade all at Pret A Manger, Pearse Street Station, Westland Row, Dublin 2, Ireland, D02 RV00, which is part of a protected structure (RPS Reg ref. 8520).
WEB2503/26received 17 Jun 2026388 m away
- Pret A Manger, Pearse Street Station, Westland Row, Dublin 2, D02 RV00 Application declared invalid
PROTECTED STRUCTURE: RETENTION: Carebrook Partnership Ltd. is applying to Dublin City Council for retention permission for illuminated signage advertising Pret A Manger café outlet to the north-west (front façade) of the building including two internally illuminated roundal signs on two doors and two internally illuminated projecting signs on the brick facade all at Pret A Manger, Pearse
Street Station, Westland Row, Dublin 2, Ireland, D02 RV00, which is part of a protected structure (RPS Reg ref. 8520).
WEB2487/26received 16 Jun 2026decided 16 Jun 2026388 m away
`description` is truncated at source (80 chars for DLR, 70 for Fingal) and `applicant` is null nationally — NPAD publishes neither in full.