PlanningRegister.ie
South Dublin County Council · SDZ22A/0007 · SDZ Application

Adamstown Boulevard Development Area Phase 1

423 homes9 storeysLucan, South Dublin County Council

97 built, 160 under construction of 257 permitted homes (Q2 2026).

Also known as Adamstown Boulevard.

  1. 6 May 2022Received
  2. 3 Oct 2022Approved
  3. 15 Apr 2024Building started
  4. 15 Jul 2025Signed off
Status
Building started
Decision
Approved · 3 Oct 2022
Size
423 homes · up to 9 storeys
Uses
residential, houses, apartments
Site
9.61 ha

Building progress councils’ figures, Q2 2026

  1. 2022Approved
  2. 2024Building started
  3. 2025First homes signed off4 sign-offs

97 built, 160 under construction of 257 permitted homes (Q2 2026).

257
homes permitted
257
homes started on site
97
homes completed

completed · under construction · not started · 257 houses and 0 apartments permitted

Quarter by quarter
QuarterPermittedUnder constructionCompletedCompleted share
Q2 202525724116
Q3 202525722532
Q4 202525716592
Q1 202625716097
Q2 202625716097

The scheme

This development comprises Phase 1 of the Adamstown Boulevard Development Area in Lucan. It proposes 423 residential units consisting of a mix of houses and apartments ranging from 2 to 9 storeys in height.

it proposes 423 residential units within the Adamstown Strategic Development Zone

What the register says

Comprising Phase 1 of the Adamstown Boulevard Development Area and consists of 38,768.21sq.m. of residential development to be constructed in a mix of housing and apartment units, with 423 residential units proposed in total (of which 166 units are subject to the application for outline permission); The housing units for which permission is being sought are on a site of 9.22Ha shall comprise 75 two bedroom units, 113 three bedroom units and 69 four bedroom units, ranging from 2 to 3 storeys in height; Outline permission is sought on a site of 0.54Ha for the apartment block, which shall range from 5 to 9 storeys in height and comprises 11 studio units, 76 one bedroom units and 79 two bedroom units; All residential units are provided with private open space, in the form of private rear gardens or balconies; The proposed development includes approximately 0.95 Ha of public open space in the form of a linear open space located on the east of the site stretching between Adamstown Way and Station Road and a pocket park located in the north-west of the site. 488 car parking spaces are proposed in total. 433 of these are allocated to the housing element of the development, and 55 are allocated to the apartments. A total of 52 visitor spaces are provided across the site; A total of 6 disabled spaces and 6 EV spaces are proposed. 40 secure bicycle parking spaces are provided in 4 locations throughout the site. 3 ESB Substations are also provided; Vehicular access to serve the development is provided from the existing Adamstown Avenue and Adamstown Way from the west and north, Station Road to the south and Stream Road, which bisects the Boulevard Development Area. A new bus turning circle, along with bus lay-bys are proposed on the south of the site on Station Road; The development includes the provision of ancillary site development works, boundary treatments and landscape works; This development amends aspects at the interface between the proposed development and the development at The Crossings currently under construction and permitted under Reg. Ref. SDZ20A/0017 (as amended by SDZ21A/0021) on lands bounded generally to the north by Adamstown Way and the Aderrig Development Area, currently under development subject to planning permissions Reg. Ref. SDZ20A/0017 (as amended by SDZ21A/0021) and Reg. Ref. SDZ21A/0014; to the east by currently undeveloped lands within the Adamstown Station Development Area as well as the railway overpass and its approach road known locally as 'the farmer's bridge'; to the south by the existing railway line and to the west by undeveloped agricultural lands; This application is being made in accordance with the Adamstown Planning Scheme 2014, as amended, and relates to a proposed development within the Adamstown Strategic Development Zone Planning Scheme Area, as defined by Statutory Instrument No. 272 of 2001

Summary from the register record.

Planning timeline 5 steps

  • 6 May 2022
    Application lodged — DZ
  • 6 Sept 2022
    Council decision — Grant
  • 2 Oct 2022
    Final approval
  • 15 Apr 2024
    Building started
  • 16 Nov 2027
    Approval runs out (estimate)

The site 9.61 ha

Boundary of Adamstown Boulevard Development Area Phase 1 as the Dublin councils map it in the housing pipeline.

Planning applications inside the site 5 applications in the last 10 years

Appeals inside the site 2 with An Coimisiún Pleanála

Building work started inside the site 4 commencement notices

Other big developments nearby within 2 km