Cookstown Industrial Estate

Building: first homes signed off Nov 2023, of 1,104 apartments.

11 storeysAbsolute Limousines Ltd and Boherkill Property Development LtdDublin 24, South Dublin County Council

Email me when the next phase is lodged

Status
Building started
Decision
Refuse permission · 8 Jul 2021
Height
up to 11 storeys
Uses
apartments, office, retail, creche, mixed
Applicant
Absolute Limousines Ltd and Boherkill Property Development Ltd · 1 planning application
Site
5.51 ha

Is it built?

  1. Not yetApproved
  2. 2023Building started
  3. 2023First homes signed off2 sign-offs

The scheme

Absolute Limousines Ltd and Boherkill Property Development Ltd propose a mixed-use development at Cookstown Industrial Estate. The project includes 1104 build-to-rent apartments across four blocks ranging from four to eleven storeys. It also features commercial units, office space, a creche, and associated infrastructure works.

What the register says

(i) Demolition of the existing industrial and commercial buildings (15,989sq.m); (ii) construction of a mixed-use development featuring: (a) 1104 'build-to-rent' apartments in 4 blocks varying in height from four to eleven storeys. Each apartment has associated private open space in the form of a ground floor terrace or a balcony and has access to internal communal amenity spaces (totalling 2741sqm) and 5,107sqm of external communal amenity space at ground, first floor and roof levels; and (b) 4 commercial units at ground floor level of Blocks B and D (comprising of 2 in Block B accommodating a cafe/restaurant/bar; 1 in Block D accommodating Class 1, 2 and 8 uses as per the Planning and Development Regulations, 2001-2019, as amended; and 1 in Block D to serve the Circle K Belgard petrol station which is to be retained), 1,500sqm of office space across first to sixth floor levels of Block D and a crèche with external play area at ground floor level of Block C. The development is served by a total of 351 parking spaces (including 17 limited mobility parking spaces and 16 car share spaces) and 1860 bicycle spaces (1464 resident spaces and 396 visitor spaces); (iii) road, junction and streetscape upgrade works along First Avenue, Cookstown Road and Old Belgard Road, including the installation a signalised junction at the intersection of First Avenue and Cookstown Road and Old Belgard Road and Cookstown Road; (iv) construction of 3 new roads and 1 pedestrian/cycle link to the Belgard Luas Stop; (v) construction of a 1,688sqm landscaped public plaza with an outdoor flexible events space in the south-western corner of the site; and (vi) associated site and infrastructural works are also proposed which include: foul and surface water drainage; attenuation tanks; lighting; landscaping; boundary fences; plant areas; ESB substations; internal hard landscaping, including footpaths and street furniture; and all associated site development works. Any person may, within the period of 5 weeks beginning on the date of receipt by An Bord Pleanála of the application and on payment of the prescribed fee of €20 (except for certain prescribed bodies), make a submission or observations in writing to An Bord Pleanála, 64 Marlborough Street, Dublin 1 or online at www.pleanala.ie. Any enquiries relating to the application process should be directed to the Strategic Housing Development Section of An Bord Pleanála (Tel. 01-8588100)

Summary from the register record.

Planning timeline
  1. 19 Mar 2021Received
  2. 8 Jul 2021Refuse permission

The site 5.51 ha

Boundary of Cookstown Industrial Estate from the planning application.

Planning applications inside the site 16 applications in the last 10 years

Show 8 more
Appeals inside the site 9 with An Coimisiún Pleanála
Commencement notices inside the site 5