Dublin City Council · 4778/22

27-29 New Row South, Dublin 8

Approved in Apr 2024. Building started in 2024.

  1. 2 Sept 2022Received
  2. 26 Jan 2023Approved
  3. 22 Feb 2023Appealed
  4. 26 Apr 2024Appeal: Approved with conditions
  5. 4 Nov 2024Building started
  6. 2 Jan 2026Final approval

Planning details

Status
Building startedi
Decision
Approved · 26 Jan 2023
Reference
4778/22
Received
2 Sept 2022
Further information
Requested 27 Oct 2022 · received 21 Dec 2022
Site
2,247 m²
Appeal
ACP 315887 · Approved with conditions

What’s proposed

PROTECTED STRUCTURE: Permission for modifications to the mixed use development permitted under Reg. Ref.: 4423/19 & ABP Ref.: 307217-20 . The application site is located at the junction of New Row South to the northwest , Blackpitts to the west and Fumbally Lane to the south and southeast. The site contains a protected structure (referred to as a former laundry building under RPS ref 5821) .

Show all

The proposed modifications to the permitted development consist of the following: • Change of use of the 69 no. permitted single occupancy shared accommodation units and amenity spaces from fourth to seventh floor level and extension to permitted 7th floor level to provide 86 no. hotel bedrooms. • Internal alterations to permitted first to third floor level to provide 5 no. additional hotel bedrooms on previously permitted floors. • The proposed development will increase the total number of permitted hotel rooms to 235 no. rooms. • Internal alterations to permitted ground floor level including the removal of residential lounges, gym, restaurant and public community/event space. • The proposed ground floor level comprises co-working, café/restaurant event space, hotel reception, lounges areas and ancillary back of house areas. • Omission of the basement and relocation of plant to an enclosure at 7th floor level. • Provision of 3 no. new window openings to the existing building, a Protected Structure under RPS Ref.: 5821, minor alterations to the previously permitted works to the façade to the Protected Structure including reconfiguration of main entrance points and modifications to the fenestration at first floor level. • The proposed development includes elevational changes to the permitted 8 storey building to the southwest of the site including enclosure of the multi-storey staircase. Provision of a c. 1.4 metre pop- up area at roof level for ventilation purposes and increased parapet height of the building by 300mm to accommodate blue roof system. • Reduction in cycle parking provision at ground floor level. • All associated development

42 other applications within 500 m in the last year · 1 open for comments

Open the report

Nearby 42 · 500 m · 12 months

Distance
Time
Show all 42

Explore this area on the map →

Homes nearby

Development land nearby

See all development land near here →

Appeal

ACP 315887 · Planning Appeal · decided · Approved with conditions 26 Apr 2024
received by the Commission 22 Feb 2023 · inspector's report · board order

Building started

  • 24 Jul 2025 · Builder told the council work was starting CN0131399DC
  • 4 Nov 2024 · Builder told the council work was starting CN0121633DC

Zoning

Zone Z6 - DEV PLAN 2022-2028

C2.1 — Economic development and employment

Zoned for employment uses. Housing is not the intended use here.

R2 — Existing residential

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

Protections nearby 250 m

Flood area nearby (OPW maps). floodinfo.ie ↗

  • NIAH-recorded building · 28
    house; Vivid Hair & Beauty
  • Recorded monument · 54
    Gateway; Bridge
Where this comes from

National planning feed (NPAD), fetched 11 Sept 2026, 18:51.

Source: National Planning Application Database · fetched 11 Sept 2026, 18:51
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.011 Sept 2026, 18:51open
Summary

4778/22 is a planning application to Dublin City Council for PROTECTED STRUCTURE: Permission for modifications to the mixed use development permitted, received on 2 Sept 2022; permission was granted on 26 Jan 2023.