South Dublin: homes with planning permission that nobody has started
Data updated 26 Sept 2026 · register lag up to 7 days · sources & freshness
25,842 homes in 186 sites of 10 or more have been granted permission in South Dublin since 2017. A commencement notice was lodged for 59% of them. 8,645 still have a live permission and no start; 552 of those lapse within a year, and 1,851 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By local electoral area 7
| Local electoral area | Sites | Homes permitted | Started | Not started | Lapsing | Lapsed |
|---|---|---|---|---|---|---|
| Lucan | 34 | 6,347 | 52% | 2,575 | — | 485 |
| Clondalkin | 60 | 9,056 | 68% | 2,038 | — | 766 |
| Firhouse-Bohernabreena | 27 | 2,869 | 43% | 1,289 | 131 | 345 |
| Rathfarnham-Templeogue | 13 | 1,951 | 48% | 1,024 | — | — |
| Tallaght Central | 20 | 2,506 | 64% | 841 | — | 31 |
| Tallaght South | 20 | 2,122 | 70% | 546 | 421 | 97 |
| Palmerstown-Fonthill | 12 | 991 | 54% | 332 | — | 127 |
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2017 | 19 | 828 | 80% | 0 | 166 |
| 2018 | 31 | 2,063 | 78% | 11 | 436 |
| 2019 | 16 | 1,877 | 68% | 0 | 605 |
| 2020 | 19 | 3,103 | 85% | 224 | 231 |
| 2021 | 9 | 842 | 46% | 170 | 286 |
| 2022 | 14 | 2,360 | 77% | 552 | — |
| 2023 | 26 | 4,678 | 89% | 375 | 127 |
| 2024 | 13 | 1,890 | 57% | 815 | — |
| 2025 | 13 | 2,893 | 46% | 1,532 | — |
| 2026 | 26 | 5,308 | 4% | 4,966 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 30 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 94% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| Cairn Homes Properties Limited | 18 | 4,880 | 67% | 1,332 | 172 |
| South Dublin County Council | 1 | 1,252 | 0% | 1,252 | — |
| Kelland Homes Limited | 5 | 1,227 | 31% | 844 | — |
| Steeplefield Limited | 1 | 588 | 0% | 588 | — |
| Lagan Homes Ballycullen Limited | 1 | 502 | 0% | 502 | — |
| Hugh McGreevy & Sons Limited | 1 | 453 | 0% | 453 | — |
| Watfore Limited | 1 | 436 | 0% | 436 | — |
| Shannon Homes Dublin Unlimited Company | 1 | 402 | 0% | 402 | — |
| Evara Developments Limited | 5 | 438 | 16% | 368 | — |
| Quintain Developments Ireland Limited | 6 | 1,467 | 76% | 355 | — |
| Cape Wrath Hotel Unlimited Company | 1 | 224 | 0% | 224 | — |
| Stranwil Limited | 1 | 204 | 0% | 204 | — |
| Midsal Homes Limited | 1 | 199 | 0% | 199 | — |
| Square Foot Property Services Limited | 1 | 170 | 0% | 170 | — |
| ARP 4.2 Sustainable Communities (Ireland) Fund | 1 | 169 | 0% | 169 | — |
| MacCabe Durney Barnes Limited | 1 | 131 | 0% | 131 | — |
| Propiteer Ibis Red Cow Limited | 1 | 115 | 0% | 115 | — |
| Bluemont Developments (Firhouse) Limited | 1 | 100 | 0% | 100 | — |
| Kingscroft Developments Limited | 1 | 90 | 0% | 90 | — |
| Greenacre Residential DAC | 2 | 610 | 0% | 86 | 524 |
| Anthony Neville Homes Limited | 1 | 73 | 0% | 73 | — |
| Clear Real Estate Holdings Limited | 1 | 63 | 0% | 63 | — |
| Emmaville Limited | 1 | 55 | 0% | 55 | — |
| Seabren Developments Limited | 1 | 55 | 0% | 55 | — |
| Hollyville Investments Limited | 1 | 43 | 0% | 43 | — |
| Deane and Deane Limited | 1 | 30 | 0% | 30 | — |
| Cavan Developments Limited | 1 | 28 | 0% | 28 | — |
| Old Nangor Road Limited | 1 | 26 | 0% | 26 | — |
| Ballymount Homes Limited | 1 | 22 | 0% | 22 | — |
| Fitzgibbon Brothers Limited | 1 | 20 | 0% | 20 | — |
Permission, no start 43 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
Unbuilt permissions in South Dublin, site by site · Stalled schemes in South Dublin on Buildable
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Kishoge Development Area Sites 3, 4 and 5 SDZ25X/0001 | 1,252 | 31 Mar 2026 | Not started lapses in 5 years | Lucan |
| Boherboy, Saggart LRD25A/0012W | 611 | 25 Jun 2026 | Not started lapses in 5 years | Boherboy |
| Former Chadwicks Builders Merchant LRD25A/0005W | 588 | 13 May 2026 | Not started lapses in 5 years | Greenhills |
| Woodtown Development LRD25A/0003W | 502 | 6 Mar 2026 | Not started lapses in 4 years | Woodtown |
| Kishoge Urban Centre SDZ25A/0012W | 494 | 25 Aug 2025 | Not started lapses in 4 years | Clondalkin |
| Tubber Lane Residential Development SDZ26A/0008W | 453 | 5 May 2026 | Not started lapses in 5 years | Lucan |
| Parkmore Industrial Estate LRD25A/0002W | 436 | 4 Dec 2025 | Not started lapses in 4 years | Rathfarnham-Templeogue |
| Taylor's Lane and Edmondstown Road LRD23A/0002 | 402 | 22 Sept 2025 | Not started lapses in 4 years | Ballyboden |
| Aderrig Phase 4 SDZ24A/0011 | 355 | 20 Jun 2024 | Not started lapses in 3 years | Lucan |
| Cappagh SDZ24A/0019W | 318 | 2 Sept 2024 | Not started lapses in 3 years | 11th Lock |
| Clonburris Residential Development SDZ25A/0019W | 233 | 23 Mar 2026 | Not started lapses in 4 years | Neilstown |
| Garters Lane Development SHD3ABP-308088-20 | 224 | 21 Dec 2020 | Not started lapses in 4 years | Saggart |
| The Crossings Phase 3 SDZ25A/0050W | 214 | 22 Jun 2026 | Not started lapses in 5 years | Lucan |
| Cookstown Industrial Estate LRD23A/0006 | 204 | 16 Oct 2023 | Not started lapses in 2 years | Tallaght Central |
| Belgard Square East LRD25A/0009W | 199 | 27 May 2026 | Not started lapses in 5 years | Tallaght |
| Glen Abbey Complex SHD3ABP-309916-21 | 170 | 21 Sept 2021 | Not started lapses in 4 years | Tallaght |
| Whitestown Way Development LRD26A/0002W | 169 | 1 Sept 2026 | Not started lapses in 5 years | Tallaght Central |
| Ibis Hotel and Monastery Gate SHD3ABP-314701-22 | 115 | 28 Jul 2023 | Not started lapses in 2 years | Clondalkin |
| Tandy's Lane Village Phase 3 SDZ26A/0004W | 107 | 31 Mar 2026 | Not started lapses in 5 years | Lucan |
| 2 Firhouse Road and Former Morton's The Firhouse Inn LRD26A/0001W | 100 | 10 Aug 2026 | Not started lapses in 5 years | Firhouse |
| Units 66 and 67 LRD26A/0004W | 99 | 10 Sept 2026 | Not started lapses in 5 years | Tallaght |
| Citywest Avenue Development SD24A/0279W | 90 | 25 Mar 2025 | Not started lapses in 3 years | Tallaght South |
| Fortunestown Lane and Parklands Parade LRD24A/0006W | 86 | 1 Nov 2024 | Not started lapses in 3 years | Saggart |
| Kishoge Southwest Development Area SDZ25A/0044W | 84 | 17 Sept 2026 | Not started lapses in 5 years | Lucan |
| Drury Mills and Drury Park Extension SD24A/0092W | 73 | 10 Feb 2026 | Not started lapses in 4 years | Millbridge Cross |
| C. 09 ha landholding SDZ26A/0013W | 63 | 28 Jul 2026 | Not started lapses in 5 years | Lucan |
| Scholarstown House SD25A/0150W | 55 | 2 Jun 2026 | Not started lapses in 5 years | Scholarstown |
| Speaker Connolly Tavern SD24A/0228W | 55 | 11 Aug 2025 | Not started lapses in 4 years | Firhouse |
| A site of approximately 5.12 Ha, in the townlands of Gollierstown and Finnstown SDZ26A/0009W | 47 | 11 Aug 2026 | Not started lapses in 5 years | Lucan |
| Main Street & New School Road SD24A/0071 | 44 | 12 Mar 2026 | Not started lapses in 4 years | Peamount Cross |
| junction of Kennelsfort Road Upper SD24A/0221W | 43 | 6 May 2025 | Not started lapses in 4 years | Palmerstown-Fonthill |
| Main Street SD22A/0286 | 30 | 26 Nov 2024 | Not started lapses in 3 years | Peamount Cross |
| Rathmill Manor SD25A/0134W | 28 | 24 Feb 2026 | Not started lapses in 4 years | Clondalkin |
| Finches Shopping Centre SD22A/0346 | 26 | 7 Aug 2024 | Not started lapses in 3 years | Palmerstown-Fonthill |
| playing pitch at SD22A/0365 | 22 | 11 Jan 2023 | Not started lapses within a year | Firhouse-Bohernabreena |
| Larkfield Square SD25A/0203W | 20 | 24 Feb 2026 | Not started lapses in 4 years | Palmerstown-Fonthill |
| McEvoys Public House SD25A/0146W | 15 | 27 Jan 2026 | Not started lapses in 4 years | Peamount Cross |
| Gordon Park SD23A/0016 | 13 | 3 May 2023 | Not started lapses in 2 years | Tallaght South |
| Citywest Village SD25A/0051W | 12 | 2 Sept 2025 | Not started lapses in 4 years | Fortunestown |
| Rookwood SD21A/0202 | 11 | 24 Oct 2023 | Not started lapses in 2 years | Firhouse-Bohernabreena |
| Vista Montana SD17A/0364 | 11 | 4 May 2018 | Not started lapses in 5 years | Knocklyon |
| Newlands Road SD25A/0193W | 10 | 28 Jul 2026 | Not started lapses in 5 years | Palmerstown-Fonthill |
| Combined sites of 'The Priory' and 'Leabeg' SD21A/0290 | 10 | 6 Dec 2023 | Not started lapses in 2 years | Marlfield |
How it is counted
- A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'SDCC' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 26 Sept 2026, 07:08
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
| An Coimisiún Pleanála case list | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
| Building Control Management System commencement notices | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
Recomputed weekly from the store; last built 26 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.