Tipperary planning permission: the homes nobody has started
Data updated 6 Nov 2026 · register lag up to 7 days · sources & freshness
2,345 homes in 58 sites of 10 or more have been granted permission in Tipperary since 2021. A commencement notice was lodged for 66% of them. 703 still have a live permission and no start; — of those lapse within a year, and 14 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By local electoral area 8
| Local electoral area | Sites | Homes permitted | Started | Not started | Lapsing | Lapsed |
|---|---|---|---|---|---|---|
| Clonmel | 22 | 904 | 62% | 269 | — | — |
| Carrick-On-Suir | 8 | 220 | 32% | 136 | — | 14 |
| Cashel-Tipperary | 5 | 266 | 60% | 106 | — | — |
| Thurles | 3 | 134 | 28% | 96 | — | — |
| Nenagh | 14 | 638 | 89% | 71 | — | — |
| Roscrea-Templemore | 3 | 101 | 75% | 25 | — | — |
| Cahir | 2 | 69 | 100% | 0 | — | — |
| Newport | 1 | 13 | 100% | 0 | — | — |
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2021 | 5 | 211 | 93% | 0 | 14 |
| 2022 | 10 | 258 | 96% | 10 | — |
| 2023 | 12 | 567 | 92% | 48 | — |
| 2024 | 12 | 631 | 81% | 120 | — |
| 2025 | 10 | 404 | 14% | 347 | — |
| 2026 | 9 | 274 | 8% | 178 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 19 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 37% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| O'Ceallaigh Westfield Limited | 1 | 52 | 0% | 52 | — |
| Rockspring Developments Limited | 1 | 41 | 0% | 41 | — |
| Greenrise Developments Limited | 2 | 40 | 0% | 40 | — |
| Bluemont Developments (Clonmel) Limited | 1 | 35 | 0% | 35 | — |
| JSF Property Holding Limited | 3 | 116 | 78% | 25 | — |
| Dromineer Bay Developments Limited | 1 | 14 | 0% | 14 | — |
| Belindere Homes Limited | 1 | 11 | 0% | 11 | — |
| Torca Developments Limited | 1 | 122 | 100% | 0 | — |
| Crann Ard Developments Limited | 2 | 92 | 100% | 0 | — |
| Lisbunny Developments Limited | 1 | 67 | 100% | 0 | — |
| Brinkley Homes Limited | 2 | 57 | 100% | 0 | — |
| Coalquay Developments Limited | 2 | 42 | 100% | 0 | — |
| Liberty Square Consulting Limited | 1 | 38 | 100% | 0 | — |
| Montpellier Drummin Developments Limited | 1 | 36 | 100% | 0 | — |
| SMJ Developments Limited | 1 | 33 | 100% | 0 | — |
| Norris Real Estate Holdings Limited | 1 | 29 | 100% | 0 | — |
| Hallclon Properties Limited | 1 | 21 | 100% | 0 | — |
| Singland Homes Limited | 1 | 18 | 100% | 0 | — |
| Mulcahy Properties Limited | 1 | 10 | 100% | 0 | — |
Work started 35 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Croan Lower Coleville Road 2460316 | 122 | 20 Jun 2024 | Started notice 24 Dec 2024 | Clonmel |
| Wallers Lot / Hughes Lot East 2361027 | 117 | 20 May 2024 | Started notice 20 Jun 2024 | Cashel-Tipperary |
| Dromin Road 2360274 | 98 | 31 Oct 2023 | Started notice 2 Mar 2026 | Nenagh |
| Tyone 2260181 | 92 | 13 Feb 2023 | Started notice 16 Sept 2026 | Nenagh |
| Dromin Road 2260527 | 91 | 31 Jul 2023 | Started notice 6 Feb 2026 | Nenagh |
| Moangarriff 2260353 | 68 | 15 Nov 2022 | Started notice 9 Apr 2024 | Clonmel |
| Dromin Road 2360273 | 67 | 6 Nov 2023 | Started notice 29 Apr 2026 | Nenagh |
| Tyone 21959 | 67 | 27 Sept 2021 | Started notice 19 Apr 2024 | Nenagh |
| Drummin 2360551 | 63 | 15 Apr 2024 | Started notice 6 Apr 2026 | Nenagh |
| Glencarra Estate Fethard Road 21636 | 55 | 30 Nov 2021 | Started notice 7 Oct 2024 | Clonmel |
| Knockeevan 2460498 | 50 | 17 Dec 2024 | Started notice 30 Dec 2024 | Clonmel |
| Inishlounaght 2260698 | 49 | 23 Aug 2023 | Started notice 31 Dec 2024 | Clonmel |
| Lissava 211049 | 45 | 8 Nov 2022 | Started notice 14 Oct 2024 | Cahir |
| Sir Johns Road 2460730 | 41 | 28 Nov 2024 | Started notice 27 Dec 2024 | Carrick-On-Suir |
| Glenconnor 2360415 | 41 | 1 Nov 2023 | Started notice 20 Nov 2023 | Clonmel |
| New Row Kiltillane 2460342 | 40 | 22 Oct 2024 | Started notice 15 Aug 2025 | Roscrea-Templemore |
| Thurles townparks Bohernamona and Bowling Green 21279 | 38 | 21 Sept 2021 | Started notice 16 Dec 2024 | Thurles |
| Crann Ard and Glencarra Estates 21515 | 37 | 22 Nov 2021 | Started notice 7 Oct 2024 | Clonmel |
| New Row 2360219 | 36 | 5 Mar 2024 | Started notice 15 Aug 2025 | Roscrea-Templemore |
| Drummin Village 211348 | 36 | 1 Feb 2022 | Started notice 20 Mar 2023 | Nenagh |
| Dromin Road 2260564 | 35 | 29 Oct 2023 | Started notice 16 Mar 2026 | Nenagh |
| Plots no. 21-29 38 41-63 Limetree Grove 2460977 | 33 | 19 Feb 2025 | Started notice 31 Dec 2024 | Cashel-Tipperary |
| Glenconnor 2460042 | 29 | 17 Apr 2024 | Started notice 14 Jun 2024 | Clonmel |
| Rosemount Farm Road 2460828 | 24 | 10 Sept 2025 | Started notice 25 Feb 2026 | Cahir |
| Ivowen 2260272 | 24 | 6 Oct 2022 | Started notice 6 Jun 2023 | Clonmel |
| Prior Park Grove 2560701 | 21 | 15 Jan 2026 | Started notice 28 Apr 2026 | Clonmel |
| Coleville Road 21654 | 20 | 4 Jan 2022 | Started notice 22 Apr 2024 | Clonmel |
| Silversprings Road and Davis Road Junction 2360148 | 18 | 21 Jun 2023 | Started notice 3 Oct 2024 | Clonmel |
| Springfort Meadows 2360047 | 18 | 3 Apr 2023 | Started notice 28 Sept 2024 | Nenagh |
| An Seanline 21926 | 18 | 23 Feb 2022 | Started notice 11 May 2022 | Carrick-On-Suir |
| Glenconnor 2260123 | 16 | 29 Jun 2022 | Started notice 7 Oct 2024 | Clonmel |
| Lakeview Cullenagh 2360980 | 13 | 5 Sept 2024 | Started notice 17 Aug 2026 | Newport |
| Knocknaconnery 22469 | 11 | 10 Oct 2022 | Started notice 7 Apr 2025 | Carrick-On-Suir |
| Abbey Road 2360241 | 10 | 15 Aug 2023 | Started notice 1 Sept 2023 | Clonmel |
| An Duiche 211843 | 10 | 10 May 2022 | Started notice 23 Feb 2026 | Cashel-Tipperary |
How it is counted
- A site is one grant of permission for 10 or more homes since 2021: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2021 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'TIPPERARY' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 6 Nov 2026, 23:00
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC BY 4.0 | 6 Nov 2026, 23:00 | open |
| An Coimisiún Pleanála case list | CC BY 4.0 | 6 Nov 2026, 23:00 | open |
| Building Control Management System commencement notices | CC BY 4.0 | 6 Nov 2026, 23:00 | open |
Recomputed weekly from the store; last built 6 Nov 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.
Big developments by name · Where Dublin is building · Sources & freshness