Approved in Feb 2025. Building started in 2025.

  1. 31 Oct 2024Received
  2. 19 Dec 2024Approved
  3. 19 Feb 2025Final approval
  4. 6 Mar 2025Building started
Status
Building startedi
Decision
Approved · 19 Dec 2024
Council
Dublin City Council
Type
Permission
Site
104 m²

What’s proposed

Changes to front elevation with new front bay window extension and covered porch, new velux roof light to front roof, new enlarged rear bedroom window at first floor and internal alterations. All to existing 2 storey terraced house

Planning details

Reference
WEB2407/24
Local authority
Dublin City Council
Status
Commenced · register status “Decision Notice Issued”
Received
31 Oct 2024
Decision due
3 Jan 2025 · decided 19 Dec 2024
Decision
Grant permission on 19 Dec 2024
Site area
104 m² from the mapped boundary, not the council's figure

Live near 58 Rothe Abbey?

Everything else planned on your street, in one report.

Check my street
Council register ↗

Nearby 24 · 500 m · 12 months

Distance
Time
Show all 24

Explore this area on the map →

Homes nearby

Development land nearby

See all development land near here →

Building started

  • 6 Mar 2025 · Builder told the council small works were starting CN0126050DC

Zoning

Zone Z1 - DEV PLAN 2022-2028

R2 — Existing residential

An established residential area. The objective is to protect existing residential amenity as well as to provide housing — which is the objective a neighbour's objection to an overbearing extension is usually argued under.

Protections nearby 250 m

  • Natural Heritage Area (incl. proposed) · 1
    Grand Canal
  • NIAH-recorded building · 7
    Grand Canal; Griffith Bridge

Where this comes from

National planning feed (NPAD), fetched 11 Sept 2026, 18:51.

Source: National Planning Application Database · fetched 11 Sept 2026, 18:51
SourceLicenceFetchedLink
National Planning Application DatabaseCC BY 4.011 Sept 2026, 18:51open
Summary

WEB2407/24 is a planning application to Dublin City Council for changes to front elevation with new front bay window extension and covered porch, new, received on 31 Oct 2024; permission was granted on 19 Dec 2024.