Louth: homes with planning permission that nobody has started
Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness
13,278 homes in 211 sites of 10 or more have been granted permission in Louth since 2017. A commencement notice was lodged for 47% of them. 4,061 still have a live permission and no start; 747 of those lapse within a year, and 1,554 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By year granted
| Granted in | Sites | Homes | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| 2017 | 8 | 439 | 79% | 0 | 23 |
| 2018 | 8 | 1,321 | 95% | 0 | 62 |
| 2019 | 19 | 1,506 | 30% | 352 | 705 |
| 2020 | 16 | 1,213 | 55% | 0 | 548 |
| 2021 | 21 | 665 | 61% | 185 | 77 |
| 2022 | 27 | 1,267 | 72% | 261 | 99 |
| 2023 | 36 | 1,759 | 30% | 1,183 | 40 |
| 2024 | 26 | 1,592 | 45% | 881 | — |
| 2025 | 25 | 1,270 | 57% | 547 | — |
| 2026 | 25 | 2,246 | 9% | 652 | — |
Recent years are still open: a permission granted this year has had months, not years, to start.
Who holds the permissions 30 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 90% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| Ballymakenny Residential Properties Limited | 15 | 975 | 58% | 406 | — |
| McCaughey Homes Limited | 3 | 356 | 0% | 356 | — |
| Ballymakenny Developments Limited | 7 | 456 | 55% | 206 | — |
| F J Developments Limited | 1 | 205 | 0% | 205 | — |
| Sionna Homes Limited | 1 | 192 | 0% | 192 | — |
| Housing Section Louth County Council | 2 | 190 | 0% | 190 | — |
| McParland Bros Builders Limited | 2 | 203 | 10% | 183 | — |
| Groveview Builders Limited | 12 | 480 | 58% | 179 | 21 |
| Lorrac Developments Limited | 2 | 116 | 0% | 116 | — |
| Tapemount Limited | 1 | 99 | 0% | 99 | — |
| Dwellings Developments Drogheda Limited | 2 | 179 | 45% | 98 | — |
| Propchain Solutions Limited | 5 | 267 | 64% | 97 | — |
| Ballymakenny SW Limited | 2 | 178 | 46% | 97 | — |
| LAJONA LIMITED | 1 | 91 | 0% | 91 | — |
| Wonderglade Unlimited Company | 4 | 258 | 66% | 89 | — |
| Independent Trustee Company Limited | 1 | 80 | 0% | 80 | — |
| Crescent Sites Limited | 1 | 58 | 0% | 58 | — |
| Urban Life (GSD) Limited | 1 | 57 | 0% | 57 | — |
| Armagh Construction Limited | 1 | 57 | 0% | 57 | — |
| Urban Life (BVH) Limited | 1 | 54 | 0% | 54 | — |
| Fichidi Lane Developments Limited | 1 | 54 | 0% | 54 | — |
| The Ardee Partnership | 2 | 117 | 56% | 52 | — |
| Birchgrange Limited | 1 | 51 | 0% | 51 | — |
| OHMG (Rol) Limited | 2 | 50 | 0% | 50 | — |
| May Ard Developments Limited | 1 | 48 | 0% | 48 | — |
| Dundalk Racing (1999) Limited | 1 | 45 | 0% | 45 | — |
| Urban Life Developments Limited | 8 | 295 | 63% | 44 | 64 |
| Burmilla Limited | 1 | 43 | 0% | 43 | — |
| Curo Developments Limited | 1 | 40 | 0% | 40 | — |
| Molaris Limited | 1 | 39 | 0% | 39 | — |
Permission, no start 77 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Lisdoo Townland 2460321 | 205 | 1 Aug 2024 | Not started lapses in 3 years | |
| Boyne Road 2360053 | 192 | 14 Dec 2023 | Not started lapses in 2 years | |
| Bellfield 2364 | 183 | 6 Apr 2023 | Not started lapses in 2 years | |
| Old Golf Links Road & Tuites Lane 181024 | 158 | 3 May 2019 | Lapsing lapses in 3 months | |
| Inner Relief Road and Dublin Road 19171 | 142 | 24 Jun 2019 | Lapsing lapses in 3 months | |
| Yellowbatter 2560797 | 99 | 13 Jul 2026 | Not started lapses in 5 years | |
| Dromena Road 2460637 | 99 | 4 Dec 2025 | Not started lapses in 4 years | |
| Twenties Lane 2360467 | 99 | 29 Jul 2024 | Not started lapses in 3 years | Moneymore |
| Twenties Lane 22713 | 99 | 19 Jun 2023 | Not started lapses in 2 years | Moneymore |
| Newtownstalaban Termonfeckin Road 2360261 | 98 | 23 Oct 2023 | Not started lapses in 2 years | |
| Greenbatter and Newtownstalaban 2660456 | 97 | 28 Aug 2026 | Not started lapses in 5 years | Greenbatter |
| Ellwood Park 2460367 | 97 | 16 Dec 2024 | Not started lapses in 3 years | |
| Ballymakenny Road 2456 | 97 | 5 Jun 2024 | Not started lapses in 3 years | |
| Mount Avenue 211173 | 93 | 12 Feb 2022 | Lapsing lapses in 5 months | |
| Armagh Road, Dundalk Co. Louth 2560399 | 91 | 2 Dec 2025 | Not started lapses in 5 years | |
| Moneymore and Yellowbatter 2360492 | 90 | 21 May 2024 | Not started lapses in 3 years | Moneymore |
| Bayview 2660089 | 89 | 11 May 2026 | Not started lapses in 3 years | |
| Dundalk Road 2560144 | 84 | 22 Dec 2025 | Not started lapses in 4 years | |
| Moneymore and Yellowbatter 2360493 | 82 | 21 May 2024 | Not started lapses in 3 years | Moneymore |
| Value Centre Cash and Carry 20661 | 80 | 6 Aug 2021 | Lapsing lapses within a year | |
| Listoke Avenue 2660283 | 72 | 4 Aug 2026 | Not started lapses in 5 years | Greenbatter |
| Listoke Avenue 2660279 | 68 | 7 Sept 2026 | Not started lapses in 5 years | Greenbatter |
| Moneymore and Yellowbatter 2360494 | 68 | 21 May 2024 | Not started lapses in 3 years | Moneymore |
| Raynoldstown Village 22688 | 65 | 7 Aug 2023 | Not started lapses in 2 years | |
| Connolly's Field 2560161 | 58 | 13 Jun 2025 | Not started lapses in 4 years | |
| Seatown Place 211390 | 58 | 4 Nov 2022 | Not started lapses in 3 years | |
| St Mary's College 22827 | 57 | 1 Sept 2023 | Not started lapses in 3 years | |
| 26 28 29 30 & 31 George's Street & Trinity Gardens 21396 | 57 | 15 Dec 2021 | Not started lapses in 2 years | Drogheda |
| Haynestown 22583 | 55 | 20 Mar 2023 | Not started lapses within a year | |
| Moneymore 2560739 | 54 | 24 Aug 2026 | Not started lapses in 5 years | Moneymore |
| Yellowbatter and Greenbatter 22894 | 54 | 27 Nov 2023 | Not started lapses in 2 years | |
| Bayview House and Bayview Cottage 2360286 | 54 | 6 Nov 2023 | Not started lapses in 2 years | |
| Bridgegate 19353 | 52 | 31 Jul 2019 | Lapsing lapses in 5 months | |
| Woodlands 24207 | 51 | 9 Jun 2025 | Lapsing lapses in 3 months | |
| Dawsons Demesne 2360237 | 48 | 21 Dec 2023 | Not started lapses in 2 years | |
| Dundalk Stadium 2560626 | 45 | 15 Jun 2026 | Not started lapses in 5 years | |
| Tullybrook Slane Road Tullyallen 2560350 | 43 | 23 Feb 2026 | Not started lapses in 4 years | |
| Termon Abbey 2360015 | 43 | 26 Oct 2023 | Not started lapses in 3 years | |
| Cord Road Greenhills Road North Strand Road 22504 | 40 | 24 Mar 2023 | Not started lapses in 3 years | |
| Dublin Road 221000 | 39 | 8 Sept 2023 | Not started lapses in 3 years | |
| Lismullen Grove 211055 | 36 | 5 Sept 2022 | Lapsing lapses within a year | |
| Termonfeckin Road Newtownstalaban 2560224 | 32 | 7 Jul 2025 | Lapsing lapses in 4 months | |
| Ballymakenny Park 2360548 | 31 | 15 May 2024 | Not started lapses in 3 years | |
| Rosehall Bog Lane 2460826 | 30 | 28 Jul 2025 | Not started lapses in 4 years | Moneymore |
| Market Street and Market House Lane 22331 | 28 | 17 Apr 2023 | Not started lapses in 3 years | |
| Knockmount 201022 | 28 | 1 Feb 2022 | Lapsing lapses in 4 months | |
| Donore Road 201165 | 28 | 16 Sept 2021 | Not started lapses within a year | |
| Greenore Road 24159 | 27 | 7 Aug 2025 | Not started lapses in 4 years | |
| Hearthfield 2360190 | 25 | 11 Sept 2023 | Not started lapses in 2 years | |
| FRANCIS STREET 2460702 | 24 | 21 Jul 2025 | Not started lapses in 4 years | |
| Yellowbatter 2460056 | 24 | 27 May 2024 | Not started lapses within a year | |
| Marlbog Road 238 | 23 | 18 May 2023 | Not started lapses in 2 years | |
| Main Street 2660270 | 22 | 30 Jul 2026 | Not started lapses in 5 years | |
| Raynoldstown Village 2460496 | 21 | 25 Aug 2025 | Not started lapses in 4 years | |
| Ardee Bread Company Castle Street 2660139 | 20 | 7 Sept 2026 | Not started lapses in 3 years | |
| Dublin Road 21205 | 20 | 4 Oct 2021 | Lapsing lapses within a month | |
| 'Hearthfield' Headford Road 2460240 | 19 | 21 Oct 2024 | Lapsing lapses in 4 months | |
| Dromiskin 22174 | 19 | 24 Feb 2023 | Not started lapses in 3 years | |
| North Road 2560625 | 18 | 16 Feb 2026 | Not started lapses in 2 years | Moneymore |
| Listoke Drive Listoke Avenue 2560017 | 17 | 7 Apr 2025 | Not started lapses in 3 years |
1–60 of 77Next 60 →
How it is counted
- A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'LOUTH' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| An Coimisiún Pleanála case list | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
| Building Control Management System commencement notices | CC-BY-4.0 | 19 Sept 2026, 07:05 | open |
Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.
Big developments by name · Where Dublin is building · Sources & freshness