PlanningRegister.ie
Permitted, not started · Longford · grants of 10+ homes since 2017

Longford: homes with planning permission that nobody has started

Data updated 19 Sept 2026 · register lag up to 7 days · sources & freshness

566 homes in 22 sites of 10 or more have been granted permission in Longford since 2017. A commencement notice was lodged for 51% of them. 237 still have a live permission and no start; 10 of those lapse within a year, and 43 have already lapsed.

566
homes permitted · 22 sites
51%
started · 286 homes
237
not started · live permission
10
lapse within 12 months
43
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By year granted

Granted inSitesHomesStartedNot startedLapsed
2017131100%0
2019512366%42
202026038%37
202136923%1043
2022112100%0
2023210787%14
20241120%12
2025614221%112
20261100%10

Recent years are still open: a permission granted this year has had months, not years, to start.

Who holds the permissions 9 named

The organisation named on the grant, ranked by homes permitted and not started. Names are on 67% of the homes in this council; a company that only appears in a council without a name source is not here. Private individuals are never named.

ApplicantSitesHomes permittedStartedNot startedLapsed
Watters Construction & Rental Limited1390%39
Beacon Assets Limited1370%37
Camlin Partnership1290%29
MFG Construction Limited25052%24
Adaview Limited193100%0
Faughnan Construction Limited261100%0
Donnelly Developments Limited130100%0
AMC Developments Limited125100%0
Avenir Homes Limited116100%0

Permission, no start 12 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Corry 2360220397 Jan 2025Not started lapses in 3 years
Dunaras & Marian Terrace/Marian Villas 20743715 Jul 2020Not started lapses in 2 years
Ballinalee 19212294 Nov 2019Not started lapses in 3 years
Rathcronan 2460286243 Mar 2025Not started lapses in 3 years
Mill Race Park & Derawley 2460271225 Feb 2025Not started lapses in 3 years
Lissanure 25281421 Oct 2025Not started lapses in 4 years
“St. Patricks Court” 2360106148 Nov 2023Not started lapses in 2 years
Drimanure 24291316 Apr 2025Not started lapses in 4 years
Church Quarter 191851310 Dec 2019Not started lapses in 3 years
Aghaboy 23602091231 Jul 2024Not started lapses in 3 years
Killashee Street & Bog Lane 2560060107 Jan 2026Not started lapses in 4 years
St Patrick's Court 21266101 Dec 2021Lapsing lapses in 2 months

How it is counted

  • A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'LONGFORD' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 19 Sept 2026, 07:05
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC-BY-4.019 Sept 2026, 07:05open
An Coimisiún Pleanála case listCC-BY-4.019 Sept 2026, 07:05open
Building Control Management System commencement noticesCC-BY-4.019 Sept 2026, 07:05open

Recomputed weekly from the store; last built 19 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.