Permitted, not started · Cork County · grants of 10+ homes since 2021

Cork County planning permission: the homes nobody has started

Data updated 13 Nov 2026 · register lag up to 7 days · sources & freshness

11,135 homes in 184 sites of 10 or more have been granted permission in Cork County since 2021. A commencement notice was lodged for 52% of them. 5,270 still have a live permission and no start; 806 of those lapse within a year, and 87 have already lapsed.

11,135
homes permitted · 184 sites
52%
started · 5,778 homes
5,270
not started · live permission
806
lapse within 12 months
87
already lapsed

All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford

By local electoral area 10

Local electoral areaSitesHomes permittedStartedNot startedLapsingLapsed
Cobh352,43649%1,24133210
Midleton402,80463%9875651
Mallow101,06524%807——
Bandon - Kinsale271,38050%69055—
Carrigaline241,36449%68723912
Fermoy1679239%48069—
Macroom1547870%128—14
Kanturk523149%117——
Bantry-West Cork412923%9942—
Skibbereen-West Cork845693%3413—

By year granted

Granted inSitesHomesStartedNot startedLapsed
20211462555%19687
2022451,93162%730—
2023402,33679%499—
2024241,60764%579—
2025301,94832%1,324—
2026312,68828%1,942—

Recent years are still open: a permission granted this year has had months, not years, to start.

Permission, no start 86 sites

Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest

SiteHomesGrantedStatusWhere
Millbrook Townparks Upper Mill Road Midleton 25/57391822 Jan 2026Not started lapses in 4 yearsMidleton
Catholic Walk Rathmore 25/40091821 Aug 2025Not started lapses in 4 yearsBandon - Kinsale
Mount Saint Josephs Back Road Pembroke Passage West Co. Cork 23/66081820 Jan 2025Not started lapses in 3 yearsCarrigaline
Blind Gate Street & Rampart Lane Town-Plots Kinsale Co Cork 23/49461815 Jan 2024Not started lapses in 2 yearsBandon - Kinsale
Friar Street & South Main Street Youghal-Lands Youghal Co.Co 24/6467161 Apr 2025Not started lapses in 3 yearsMidleton
Elmbury Carrigtohill Carrigtwohill Co Cork 24/6016164 Feb 2025Not started lapses in 3 yearsCobh
Curragh Glen 26/0412149 Sept 2026Not started lapses in 5 yearsMidleton
Cloughduv GAA Ryecourt Cloughduv Co.Cork 22/61141421 Apr 2023Not started lapses within a yearMacroom
Catherine Street 24/41491310 Jan 2025Not started lapses in 3 yearsMidleton
Gallanes Clonakilty Co. Cork 22/1151328 Jun 2022Lapsing lapses in 8 monthsSkibbereen-West Cork
Coach Road Kilworth Co. Cork 25/43621212 Feb 2026Not started lapses in 4 yearsFermoy
The Oak Water Rock Manor Water-Rock Midleton Co Cork 25/55631231 Oct 2025Not started lapses in 4 yearsCobh
Drakes Point Knocknagore Crosshaven Co.Cork 22/6519129 Jun 2023Not started lapses in 2 yearsCarrigaline
Meadstown TD 22/43741221 Mar 2023Not started lapses within a yearFermoy
Lisnagar Demesne Rathcormac Co.Cork 22/62741212 Jan 2023Not started lapses within a yearFermoy
Garranenagappul Clondrohid Macroom Co Cork 24/63731119 Sept 2025Not started lapses in 4 yearsMacroom
Gurteenroe Macroom Co. Cork 24/54331125 Oct 2024Not started lapses in 3 yearsMacroom
Lower Road Knocknagore Crosshaven Co. Cork 23/51791128 May 2024Not started lapses in 3 yearsCarrigaline
Killeagh Mills Aghadoe Killeagh Co.Cork 22/66221110 Jul 2023Not started lapses in 2 yearsMidleton
Janeville 26/13541019 Aug 2026Not started lapses in 5 yearsCarrigaline
Bishop's Island 26/07741025 Jun 2026Not started lapses in 5 yearsCobh
Carrigleigh Inchigeelagh Village Co. Cork 25/50781026 Nov 2025Not started lapses in 4 yearsMacroom
No. 3 Strand Street Youghal-Lands Youghal 23/5184107 Mar 2024Not started lapses in 2 yearsMidleton
Helm's Point Church Bay Road Crosshaven Co.Cork 23/41721018 Aug 2023Not started lapses in 2 yearsCarrigaline
former Sluagh Hall Coolbawn Town Parks [townland] Midleton 22/4298103 Feb 2023Not started lapses within a yearMidleton
Site No's 40 - 49 Garrán Ferney Kilnaglery Td. 21/6308108 Apr 2022Lapsing lapses in 5 monthsCarrigaline

← Previous 6061–86 of 86

How it is counted

  • A site is one grant of permission for 10 or more homes since 2021: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
  • Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
  • Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
  • When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
  • The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2021 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and la = 'CORKCO' group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 13 Nov 2026, 23:02
SourceLicenceFetchedLink
National Planning Application Database (NPAD)CC BY 4.013 Nov 2026, 23:02open
An Coimisiún Pleanála case listCC BY 4.013 Nov 2026, 23:02open
Building Control Management System commencement noticesCC BY 4.013 Nov 2026, 23:02open

Recomputed weekly from the store; last built 13 Nov 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.