Homes with planning permission that nobody has started
Data updated 15 Oct 2026 · register lag up to 7 days · sources & freshness
276,865 homes in 3,811 sites of 10 or more have been granted permission in Ireland since 2017. A commencement notice was lodged for 58% of them. 82,292 still have a live permission and no start; 11,263 of those lapse within a year, and 25,976 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By council 31
| Council | Sites | Homes permitted | Started | Not started | Lapsing | Lapsed |
|---|---|---|---|---|---|---|
| Dublin City | 279 | 41,493 | 58% | 9,132 | 3,752 | 8,112 |
| Fingal | 181 | 28,565 | 68% | 6,600 | 273 | 2,044 |
| South Dublin | 187 | 25,878 | 60% | 8,572 | 552 | 1,720 |
| Dún Laoghaire-Rathdown | 163 | 24,357 | 62% | 7,427 | 1,204 | 978 |
| Meath | 288 | 18,092 | 63% | 4,851 | 266 | 1,142 |
| Kildare | 263 | 15,712 | 51% | 4,148 | 1,137 | 3,063 |
| Cork County | 301 | 15,554 | 55% | 5,681 | 756 | 1,395 |
| Cork City | 167 | 15,360 | 43% | 6,880 | 544 | 1,581 |
| Louth | 215 | 13,525 | 54% | 3,520 | 580 | 1,348 |
| Wicklow | 187 | 11,243 | 59% | 3,948 | 757 | 558 |
| Limerick | 187 | 10,613 | 43% | 4,489 | 163 | 648 |
| Waterford | 119 | 6,141 | 66% | 1,546 | 28 | 322 |
| Wexford | 132 | 5,272 | 75% | 1,117 | 138 | 190 |
| Laois | 114 | 5,272 | 69% | 1,311 | 58 | 319 |
| Westmeath | 77 | 3,969 | 61% | 1,509 | 15 | 46 |
| Kerry | 84 | 3,916 | 58% | 1,009 | 48 | 105 |
| Galway City | 71 | 3,529 | 41% | 1,262 | 126 | 675 |
| Clare | 94 | 3,490 | 58% | 1,179 | 128 | 251 |
| Tipperary | 94 | 3,490 | 68% | 879 | 31 | 224 |
| Donegal | 101 | 3,348 | 49% | 1,315 | 59 | 159 |
| Kilkenny | 96 | 3,178 | 60% | 1,049 | 293 | 106 |
| Galway County | 78 | 3,142 | 56% | 1,040 | — | 199 |
| Offaly | 57 | 2,598 | 63% | 802 | 240 | 137 |
| Mayo | 62 | 1,958 | 55% | 786 | 51 | 52 |
| Sligo | 39 | 1,845 | 53% | 775 | — | 37 |
| Cavan | 52 | 1,580 | 57% | 443 | — | 174 |
| Carlow | 34 | 1,330 | 65% | 123 | 10 | 281 |
| Monaghan | 36 | 1,099 | 50% | 448 | 30 | 61 |
| Longford | 22 | 566 | 58% | 237 | 10 | — |
| Roscommon | 19 | 523 | 68% | 120 | 14 | 49 |
| Leitrim | 12 | 227 | 59% | 94 | — | — |
Sorted by homes permitted. A council with few sites is a council whose register rarely states a unit count — see how it is counted, below.
Who holds the permissions 30 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 55% of the homes in the table (from Meath, Fingal, Louth, Dublin City, Wicklow, Kildare, South Dublin, Limerick, Clare, Waterford, Kilkenny, Galway County, Kerry, Laois, Donegal, Galway City, Tipperary, Offaly, Cavan, Dún Laoghaire-Rathdown, Monaghan, Westmeath, Mayo, Sligo, Carlow, Longford, Roscommon, Leitrim, Cork City); a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| The Shoreline Partnership · Fingal | 2 | 1,951 | 0% | 1,951 | — |
| Cairn Homes Properties Limited · Dublin City, Dún Laoghaire-Rathdown, Fingal, Galway City, Kildare, Kilkenny, Meath, South Dublin, Wicklow | 31 | 6,993 | 66% | 1,859 | 488 |
| CWTC Multi Family ICAV · Dublin City | 1 | 1,614 | 0% | 1,614 | — |
| South Dublin County Council · South Dublin | 1 | 1,252 | 0% | 1,252 | — |
| Alanna Homes · Fingal | 1 | 1,243 | 0% | 1,243 | — |
| Blanche Retail Nominees Limited · Fingal | 1 | 971 | 0% | 971 | — |
| John Connaughton Limited · Meath | 1 | 810 | 0% | 810 | — |
| Shankill Property Investments Limited · Dún Laoghaire-Rathdown, Wicklow | 2 | 711 | 0% | 711 | — |
| Kelland Homes Limited · South Dublin | 1 | 611 | 0% | 611 | — |
| Noel Frisby Construction Limited · Waterford | 6 | 852 | 32% | 582 | — |
| Bovale Developments Unlimited Company · Fingal | 2 | 555 | 0% | 530 | 25 |
| Quintain Developments Ireland Limited · Fingal, South Dublin | 4 | 1,043 | 49% | 527 | — |
| The Land Development Agency · Fingal, Kildare, Limerick | 5 | 1,859 | 73% | 504 | — |
| Kingscroft Developments Limited · Kilkenny, Laois, Meath, South Dublin, Waterford | 8 | 778 | 18% | 471 | — |
| Homeland Silverpines Limited · Dún Laoghaire-Rathdown | 1 | 463 | 0% | 463 | — |
| Serendale Limited · Dublin City | 1 | 457 | 0% | 457 | — |
| Hugh McGreevy & Sons Limited · South Dublin | 1 | 453 | 0% | 453 | — |
| Ironborn Real Estate Limited · Dún Laoghaire-Rathdown | 1 | 438 | 0% | 438 | — |
| Shannon Homes Dublin Unlimited Company · South Dublin | 1 | 402 | 0% | 402 | — |
| HPREF HSQ Investments Limited · Dublin City | 1 | 399 | 0% | 399 | — |
| Beo Properties Limited · Meath | 1 | 364 | 0% | 364 | — |
| Glenveagh Homes Limited · Clare, Fingal, Kildare, Kilkenny, Meath, Offaly, South Dublin, Waterford, Westmeath, Wicklow | 40 | 5,214 | 86% | 360 | 222 |
| Trinity College Dublin · Dublin City | 1 | 358 | 0% | 358 | — |
| Keldrum Limited · Wicklow | 4 | 717 | 51% | 352 | — |
| Blanch Retail Nominee Limited · Fingal | 1 | 352 | 0% | 352 | — |
| Briargate Developments Newbridge Limited · Kildare | 2 | 329 | 0% | 329 | — |
| Jamestown Village Limited · Dublin City | 1 | 321 | 0% | 321 | — |
| Castlethorn Developments Luttrellstown Limited · Fingal | 3 | 405 | 25% | 302 | — |
| Clonkeen Investments DAC · Dún Laoghaire-Rathdown | 1 | 299 | 0% | 299 | — |
| Portmarnock Real Estate Developments Limited · Fingal | 2 | 491 | 40% | 296 | — |
Permission lapsed 372 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
Unbuilt permissions in Dublin, site by site: Dublin City · Dún Laoghaire-Rathdown · Fingal · South Dublin on Buildable
Nothing in this list.
← Previous 60421–372 of 372
How it is counted
- A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and true group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 15 Oct 2026, 23:31
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC BY 4.0 | 15 Oct 2026, 23:31 | open |
| An Coimisiún Pleanála case list | CC BY 4.0 | 15 Oct 2026, 23:31 | open |
| Building Control Management System commencement notices | CC BY 4.0 | 15 Oct 2026, 23:31 | open |
Recomputed weekly from the store; last built 15 Oct 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.
Big developments by name · Where Dublin is building · Sources & freshness