Homes with planning permission that nobody has started
Data updated 26 Sept 2026 · register lag up to 7 days · sources & freshness
269,634 homes in 3,704 sites of 10 or more have been granted permission in Ireland since 2017. A commencement notice was lodged for 54% of them. 86,000 still have a live permission and no start; 11,658 of those lapse within a year, and 29,790 have already lapsed.
All of IrelandDún Laoghaire-RathdownFingalDublin CitySouth DublinKildareMeathWicklowCarlowCavanClareCork CityCork CountyDonegalGalway CityGalway CountyKerryKilkennyLaoisLeitrimLimerickLongfordLouthMayoMonaghanOffalyRoscommonSligoTipperaryWaterfordWestmeathWexford
By council 31
| Council | Sites | Homes permitted | Started | Not started | Lapsing | Lapsed |
|---|---|---|---|---|---|---|
| Dublin City | 281 | 41,662 | 58% | 9,132 | 3,790 | 8,029 |
| Fingal | 182 | 28,601 | 66% | 6,775 | 273 | 2,398 |
| South Dublin | 186 | 25,842 | 59% | 8,645 | 552 | 1,851 |
| Dún Laoghaire-Rathdown | 162 | 24,014 | 63% | 7,079 | 1,150 | 991 |
| Meath | 274 | 16,897 | 49% | 5,373 | 385 | 2,511 |
| Cork City | 164 | 15,305 | 36% | 7,481 | 554 | 2,094 |
| Cork County | 303 | 15,204 | 55% | 5,738 | 496 | 1,103 |
| Kildare | 249 | 14,572 | 42% | 4,364 | 765 | 3,625 |
| Louth | 211 | 13,278 | 47% | 4,061 | 747 | 1,554 |
| Limerick | 184 | 10,454 | 37% | 5,005 | 441 | 813 |
| Wicklow | 167 | 10,033 | 53% | 3,674 | 905 | 578 |
| Waterford | 115 | 5,970 | 58% | 1,982 | 40 | 327 |
| Wexford | 129 | 5,150 | 75% | 1,153 | 138 | 136 |
| Laois | 108 | 4,782 | 51% | 1,623 | 226 | 689 |
| Westmeath | 76 | 3,882 | 58% | 1,631 | 32 | 12 |
| Kerry | 80 | 3,642 | 57% | 1,023 | 119 | 117 |
| Clare | 92 | 3,413 | 57% | 1,179 | 128 | 251 |
| Tipperary | 92 | 3,326 | 68% | 856 | 83 | 224 |
| Donegal | 96 | 3,172 | 45% | 1,556 | 59 | 159 |
| Kilkenny | 95 | 3,149 | 52% | 1,212 | 322 | 182 |
| Galway City | 64 | 3,094 | 36% | 1,034 | 126 | 831 |
| Galway County | 71 | 2,748 | 41% | 1,258 | — | 199 |
| Offaly | 53 | 2,449 | 49% | 929 | 142 | 308 |
| Mayo | 60 | 1,904 | 54% | 774 | 51 | 52 |
| Sligo | 38 | 1,818 | 51% | 809 | 34 | 37 |
| Cavan | 52 | 1,580 | 54% | 493 | — | 174 |
| Carlow | 34 | 1,330 | 57% | 165 | 20 | 350 |
| Monaghan | 35 | 1,073 | 43% | 474 | 56 | 91 |
| Longford | 22 | 566 | 51% | 237 | 10 | 43 |
| Roscommon | 18 | 507 | 52% | 182 | 14 | 61 |
| Leitrim | 11 | 217 | 53% | 103 | — | — |
Sorted by homes permitted. A council with few sites is a council whose register rarely states a unit count — see how it is counted, below.
Who holds the permissions 30 named
The organisation named on the grant, ranked by homes permitted and not started. Names are on 63% of the homes in the table (from Meath, Fingal, Louth, South Dublin, Kildare, Dublin City, Wicklow, Limerick, Waterford, Clare, Laois, Kilkenny, Donegal, Kerry, Galway County, Tipperary, Galway City, Westmeath, Offaly, Cavan, Mayo, Monaghan, Dún Laoghaire-Rathdown, Sligo, Carlow, Longford, Roscommon, Leitrim); a company that only appears in a council without a name source is not here. Private individuals are never named.
| Applicant | Sites | Homes permitted | Started | Not started | Lapsed |
|---|---|---|---|---|---|
| Cairn Homes Properties Limited · Dublin City, Dún Laoghaire-Rathdown, Fingal, Galway City, Kildare, Kilkenny, Meath, South Dublin, Wicklow | 45 | 10,955 | 70% | 2,623 | 579 |
| The Shoreline Partnership · Fingal | 2 | 1,951 | 0% | 1,951 | — |
| CWTC Multi Family ICAV · Dublin City | 1 | 1,614 | 0% | 1,614 | — |
| South Dublin County Council · South Dublin | 1 | 1,252 | 0% | 1,252 | — |
| Alanna Homes · Fingal | 1 | 1,243 | 0% | 1,243 | — |
| Blanche Retail Nominees Limited · Fingal | 1 | 971 | 0% | 971 | — |
| Kelland Homes Limited · Kildare, South Dublin | 6 | 1,301 | 29% | 844 | 74 |
| John Connaughton Limited · Meath | 1 | 810 | 0% | 810 | — |
| Glenveagh Homes Limited · Clare, Fingal, Kildare, Kilkenny, Meath, Offaly, South Dublin, Waterford, Westmeath, Wicklow | 41 | 5,597 | 74% | 739 | 600 |
| Shankill Property Investments Limited · Dún Laoghaire-Rathdown, Wicklow | 3 | 1,052 | 0% | 711 | — |
| Steeplefield Limited · South Dublin | 1 | 588 | 0% | 588 | — |
| Noel Frisby Construction Limited · Waterford | 6 | 852 | 32% | 582 | — |
| Bovale Developments Unlimited Company · Fingal | 2 | 555 | 0% | 530 | 25 |
| Quintain Developments Ireland Limited · Fingal, South Dublin | 7 | 1,639 | 68% | 527 | — |
| The Land Development Agency · Fingal, Kildare, Limerick | 5 | 1,859 | 73% | 504 | — |
| Lagan Homes Ballycullen Limited · South Dublin | 1 | 502 | 0% | 502 | — |
| Kingscroft Developments Limited · Kilkenny, Laois, Meath, South Dublin, Waterford | 9 | 832 | 17% | 471 | — |
| Homeland Silverpines Limited · Dún Laoghaire-Rathdown | 1 | 463 | 0% | 463 | — |
| Serendale Limited · Dublin City | 1 | 457 | 0% | 457 | — |
| Hugh McGreevy & Sons Limited · South Dublin | 1 | 453 | 0% | 453 | — |
| Ironborn Real Estate Limited · Dún Laoghaire-Rathdown | 1 | 438 | 0% | 438 | — |
| Watfore Limited · South Dublin | 1 | 436 | 0% | 436 | — |
| Ballymakenny Residential Properties Limited · Louth | 15 | 975 | 58% | 406 | — |
| Shannon Homes Dublin Unlimited Company · South Dublin | 1 | 402 | 0% | 402 | — |
| HPREF HSQ Investments Limited · Dublin City | 1 | 399 | 0% | 399 | — |
| Evara Developments Limited · South Dublin | 5 | 438 | 16% | 368 | — |
| Beo Properties Limited · Meath | 1 | 364 | 0% | 364 | — |
| Trinity College Dublin · Dublin City | 1 | 358 | 0% | 358 | — |
| McCaughey Homes Limited · Louth | 3 | 356 | 0% | 356 | — |
| Keldrum Limited · Wicklow | 2 | 619 | 43% | 352 | — |
Work started 2,023 sites
Not startedNot startedLapsingLapsedStartedUnder appealLargest firstLatest grant firstLapsing soonest
Unbuilt permissions in Dublin, site by site: Dublin City · Dún Laoghaire-Rathdown · Fingal · South Dublin on Buildable
| Site | Homes | Granted | Status | Where |
|---|---|---|---|---|
| Cherrywood DZ17A/0862 | 1,269 | 29 May 2018 | Started notice 9 Aug 2019 | Cherrywood · Dún Laoghaire-Rathdown |
| O'Devaney Gardens Site and lands previously part of St. Bric ABP-310327 | 1,047 | 13 Sept 2021 | Started notice 17 Mar 2023 | Oxmantown · Dublin City |
| Ballymakenny 17310 | 1,043 | 19 Feb 2018 | Started notice 6 Jul 2018 | Moneymore · Louth |
| Kilcarbery LRD23A/0005 | 1,033 | 5 Oct 2023 | Started notice 15 Apr 2025 | Clondalkin · South Dublin |
| Corballis East LRD0017/S3 | 1,020 | 4 Apr 2024 | Started notice 24 Apr 2024 | Corballis · Fingal |
| Ballyfermot Road ABP-313320 | 927 | 16 Nov 2022 | Started notice 18 Apr 2023 | Dublin · Dublin City |
| Clay Farm ABP-301522 | 927 | 2 Aug 2018 | Started notice 5 Nov 2018 | Glencullen-Sandyford · Dún Laoghaire-Rathdown |
| Castlelands ABP-313210 | 817 | 16 Mar 2023 | Started notice 31 Dec 2025 | Balbriggan · Fingal |
| Flemington Lane Development LRD0069/S3E | 815 | 30 Jul 2026 | Started notice 18 Sept 2026 | Clonard · Fingal |
| Lahardane 2543863 | 753 | 12 Aug 2025 | Started notice 20 May 2026 | Cork City |
| Park West Avenue and Park West Road ABP-312290 | 750 | 16 Jun 2022 | Started notice 12 Dec 2024 | Dublin · Dublin City |
| Parkside 5B ABP-312003 | 730 | 11 Apr 2022 | Started notice 8 Jul 2022 | Belmayne · Dublin City |
| Rathbourne Avenue ABP-307656 | 725 | 10 Nov 2020 | Started notice 22 Apr 2024 | Dublin · Dublin City |
| Castleforbes Business Park ABP-308827 | 702 | 31 Mar 2021 | Started notice 16 Dec 2022 | East Wall · Dublin City |
| 2.12 ha at Our Lady's Grove ABP30943021 | 698 | 3 Jun 2021 | Started notice 28 Mar 2022 | Dundrum · Dún Laoghaire-Rathdown |
| Cork Little and Shanganagh ABP-305844 | 685 | 27 Feb 2020 | Started notice 9 Jul 2021 | Killiney-Shankill · Dún Laoghaire-Rathdown |
| Development Area 9 Kishoge South East SDZ24A/0029W | 660 | 5 Aug 2025 | Started notice 6 Nov 2025 | Clondalkin · South Dublin |
| Main Street ABP-313362 | 650 | 30 Mar 2023 | Started notice 23 Sept 2024 | Swords · Fingal |
| Estuary West Lands at Holybanks LRD0018/S3E | 640 | 9 Oct 2025 | Started notice 5 Jan 2026 | Swords · Fingal |
| Zone 7 Railway, Hansfield SDZ FW18A/0110 | 618 | 7 May 2019 | Started notice 16 Oct 2019 | Pakenham Bridge · Fingal |
| Sean Moore Road PWSDZ3207/21 | 600 | 24 Mar 2022 | Started notice 22 Aug 2022 | Dublin · Dublin City |
| Grand Canal Harbour 2765/20 | 596 | 23 Nov 2020 | Started notice 19 May 2022 | Dublin · Dublin City |
| Clonburris Development Areas CUCS3 & CSWS3 SDZ22A/0018 | 594 | 31 Oct 2023 | Started notice 19 Dec 2023 | 11th Lock · South Dublin |
| Charlestown Place ABP-310350 | 590 | 16 Sept 2021 | Started notice 30 Nov 2023 | Blanchardstown-Mulhuddart · Fingal |
| Beechpark and Maryfield SHD3ABP-305878-19 | 590 | 9 Mar 2020 | Started notice 11 Dec 2020 | Scholarstown · South Dublin |
| Castletreasure 2442632 | 580 | 9 Sept 2024 | Started notice 30 Sept 2024 | Cork City |
| Hollystown-Kilmartin LRD0024/S3 | 580 | 29 Nov 2023 | Started notice 22 Dec 2023 | Blanchardstown-Mulhuddart · Fingal |
| Blakes and Esmond Motors Site ABP-300520 | 576 | 16 Mar 2018 | Started notice 11 Mar 2019 | Stillorgan · Dún Laoghaire-Rathdown |
| Former Irish Glass Bottle and Fabrizia Sites Phase 1B PWSDZ3406/22 | 570 | 8 Feb 2023 | Started notice 3 Oct 2023 | Dublin · Dublin City |
| Clonburris South West SDZ21A/0022 | 569 | 23 Aug 2022 | Started notice 30 Jan 2023 | 11th Lock · South Dublin |
| Clonburris Development Areas CSW-S1 & CSW-S2 SDZ23A/0018 | 565 | 11 Dec 2023 | Started notice 18 Sept 2024 | Clondalkin · South Dublin |
| Aldi Site ABP-305940 | 564 | 12 Mar 2020 | Started notice 8 Apr 2021 | Glencullen-Sandyford · Dún Laoghaire-Rathdown |
| 1-4 East Road ABP-304710 | 554 | 1 Oct 2019 | Started notice 22 Mar 2023 | East Wall · Dublin City |
| Dunkettle House 2443414 | 550 | 7 Aug 2025 | Started notice 23 Sept 2026 | Cork City |
| Hollystown-Kilmartin ABP-312271 | 548 | 23 Mar 2023 | Started notice 16 Aug 2023 | Blanchardstown-Mulhuddart · Fingal |
| Concorde Industrial Estate ABP-312218 | 545 | 21 Apr 2022 | Started notice 17 Apr 2024 | Drimnagh · Dublin City |
| Marmalade Lane ABP-312170 | 531 | 8 Apr 2022 | Started notice 17 Sept 2024 | Dundrum · Dún Laoghaire-Rathdown |
| Fortunestown Lane Development SHD3ABP-300555-18 | 524 | 26 Mar 2018 | Started notice 2 Jan 2019 | Saggart · South Dublin |
| Bohernabreena, Oldcourt and Killininny Development LRD24A/0007 | 523 | 8 Apr 2025 | Started notice 12 Feb 2026 | Firhouse-Bohernabreena · South Dublin |
| Techrete Site ABP-306102 | 512 | 3 Apr 2020 | Started notice 18 Apr 2023 | Howth-Malahide · Fingal |
| Former Irish Glass Bottle and Fabrizia Sites Phase 2 PWSDZ3700/24 | 502 | 5 Jul 2024 | Started notice 7 Oct 2024 | Dublin · Dublin City |
| Former Gallaher's Cigarette Factory SHD3ABP-306705-20 | 502 | 16 Jun 2020 | Started notice 10 Aug 2022 | Tallaght · South Dublin |
| Player Wills site and undeveloped Land in Ownership of Dubli ABP-308917 | 492 | 15 Apr 2021 | Started notice 28 Oct 2025 | Dublin · Dublin City |
| 2 No. sites LRD24A/0597 | 487 | 14 Apr 2025 | Started notice 25 Mar 2026 | Kilternan · Dún Laoghaire-Rathdown |
| CIE Lands ABP-305979 | 485 | 18 Mar 2020 | Started notice 13 Oct 2022 | Cabra · Dublin City |
| Golf Lane Development ABP30902620 | 482 | 20 Apr 2021 | Started notice 27 Oct 2022 | Killiney-Shankill · Dún Laoghaire-Rathdown |
| 42A Parkgate Street ABP-306569 | 481 | 28 May 2020 | Started notice 7 Apr 2021 | Dublin · Dublin City |
| Cork Little & Shanganagh LRD24A/0382/WEB | 479 | 23 Jan 2025 | Started notice 24 Apr 2025 | Killiney-Shankill · Dún Laoghaire-Rathdown |
| 'Hartfield Place' ABP-313289 | 472 | 16 Nov 2022 | Started notice 24 Apr 2024 | Dublin · Dublin City |
| City Block 3 and Northbank House DSDZ2186/20 | 472 | 26 Mar 2020 | Started notice 3 Jun 2020 | North Wall · Dublin City |
| Citywest Road and Magna Drive Development SHD3ABP-306602-20 | 463 | 26 May 2020 | Started notice 23 Jun 2021 | Tallaght South · South Dublin |
| Dorset Point 3726/20 | 447 | 24 Feb 2021 | Started notice 10 Jun 2024 | Dublin · Dublin City |
| Belgard Road and Belgard Square North SHD3ABP-303306-18 | 438 | 15 Apr 2019 | Started notice 26 Aug 2023 | Tallaght · South Dublin |
| Adamstown District Centre Phase Three SDZ23A/0025 | 436 | 28 Aug 2023 | Started notice 3 Jan 2024 | Lucan · South Dublin |
| Ratoath Road and Hamilton View ABP-306167 | 435 | 12 May 2020 | Started notice 11 Dec 2020 | Dublin · Dublin City |
| Knockgriffin 21/7265 | 434 | 16 Jun 2023 | Started notice 2 Oct 2024 | Cork County |
| Adamstown Boulevard Development Area Phase 1 SDZ22A/0007 | 423 | 3 Oct 2022 | Started notice 15 Apr 2024 | Lucan · South Dublin |
| CIE lands ABP-300492 | 420 | 20 Mar 2018 | Started notice 14 May 2019 | Cabra · Dublin City |
| Bailey Gibson Site ABP-307221 | 416 | 14 Sept 2020 | Started notice 5 Oct 2020 | Dolphin's Barn · Dublin City |
| Saint Columbans and No. 25 Hole in the Wall Road ABP-310944 | 413 | 12 Nov 2021 | Started notice 2 Dec 2022 | Dublin · Dublin City |
1–60 of 2,023Next 60 →
How it is counted
- A site is one grant of permission for 10 or more homes since 2017: the register's own unit count where the council publishes one, else the count written in the description ("48 no. apartments"). Retention, outline and extension-of-duration applications are not grants of new homes and are left out. Strategic housing developments the Board decided directly (2017–2022) come from its case list.
- Started means a commencement notice on the Building Control Management System names the permission. A notice is lodged 14 to 28 days before work begins, so this is a count of sites where building was formally begun, not of homes finished.
- Not started is a live permission with no notice. Lapsing is one that expires within 12 months; lapsed is past its expiry. The expiry is the register's where it has one, else five years from the grant (s.40 of the Planning and Development Act 2000). An extension of duration granted later is not seen here.
- When a later grant amends an earlier one on the same site (a large-scale residential development revising a strategic housing permission, a scheme quoting its parent reference) only the later one is counted, so one site is one count of homes.
- The Department's 4Dublin pipeline counts every permitted unit from 2016 and reports 41.9% "activated" at Q2 2026; this table counts sites of 10+ from 2017 and starts on the permission itself, so the two will not match to the unit. The point is the map, not the total: which sites, where, and when they lapse.
The SQL behind the table
select la, count(*) as sites, sum(units) as homes, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'started') as started, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'unbuilt') as unbuilt, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsing') as lapsing, sum(units) filter (where status /* started when a BCMS notice matches; else lapsed / lapsing (expiry within 365 days) / unbuilt by expiry_at; appealed when an appeal is still open */ = 'lapsed') as lapsed from pipeline_site where superseded_by is null and true group by la order by homes desc
Sources: National Planning Application Database (NPAD), An Coimisiún Pleanála case list, Building Control Management System commencement notices · fetched 26 Sept 2026, 07:08
| Source | Licence | Fetched | Link |
|---|---|---|---|
| National Planning Application Database (NPAD) | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
| An Coimisiún Pleanála case list | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
| Building Control Management System commencement notices | CC-BY-4.0 | 26 Sept 2026, 07:08 | open |
Recomputed weekly from the store; last built 26 Sept 2026. Status (started, lapsing, lapsed) moves with the calendar between builds.
Big developments by name · Where Dublin is building · Sources & freshness